USC55 - Layout

USC55 - Layout. USC55 – HC Equipment. Power Converters Collimators Beam Instrumentation Quench Protection System Energy Extraction System Cryogenics Controls Magnets Access & Safety Personnel Safety. USC55- Hardware Commissioning Programme 5L. Week 10. Week 11. Week 12. Week 13.

tillie
Download Presentation

USC55 - Layout

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. USC55 - Layout

  2. USC55 – HC Equipment Power Converters Collimators Beam Instrumentation Quench Protection System Energy Extraction System Cryogenics Controls Magnets Access & Safety Personnel Safety

  3. USC55- Hardware Commissioning Programme 5L Week 10 Week 11 Week 12 Week 13 March 2007 Interconnection 60 A Orbit Correctors Beam Instrumentation Cryo Valves manipulation QPS HV Tests Cryo-Instrumentation Cables HV Tests CL Heater Functional Tests CL Insulation Vacuum ELQA-GII Free Week 14 Week 15 Week 16 Week 17 Pump Down Leak Tests April 2007 ELQA-TP4-A ELQA-GII Consolidation after Pressure Tests Tentative dates to be confirmed Pressure Tests Free Week 18 Week 19 Week 20 Week 21 May 2007 Flushing ElQA@Warm Free

  4. USC55- Hardware Commissioning Programme 5L Week 22 Week 23 Week 24 Week 25 Cooldown 80-1.9 K June 2007 Cooldown 300-80K Controlled by Cryo Operation Point 4 & Point 5 Week 26 Week 27 Week 28 Week 29 & 30 July 2007 Cooldown 80-1.9 K Tentative dates to be confirmed ElQA@20K ElQA@1.9K Controlled by Cryo Operation Point 4 & Point 5 Week 31 … … Week 40 Aug.- Sept.- Oct 2007 Powering tests Controlled by Hardware Commissioning Point 4 & Point 5

  5. powering tests: shifts & meetings in the CCC 16.30 8.30 HCC EIC POC MPP CPP MELC Soft EL VAC ACR PIC CV 22.00 7.00 15.00 morning shift afternoon shift Hardware Commissioning Coordination Meeting

  6. the CCC & the field EIC POT POI Cryo QPS QPS PIC EE EE OP POE QPS/EE HCC MPP CPP Mr Circuit MEL-CF VAC ACR PIC CO CV EL AB-OP & HCC AB-OP FCR Point8 then CCC 2 shifts the field Equipment owners on-call during normal working hours good will outside normal working hours piquet