LBT Q1 2007 Engineering Review Swing Arms (SWA) Gusick

LBT Q1 2007 Engineering Review Swing Arms (SWA) Gusick. Open Issues. Technical Swing arm shock absorber Schedule PF Swing Arm Commissioning Financial None Resource Telescope Time/Manpower – Telescope at horizon for ADSEC swing arm wiring and testing

orde
Download Presentation

LBT Q1 2007 Engineering Review Swing Arms (SWA) Gusick

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q1 2007 Engineering Review Swing Arms (SWA)Gusick

  2. Open Issues • Technical • Swing arm shock absorber • Schedule • PF Swing Arm Commissioning • Financial • None • Resource • Telescope Time/Manpower – Telescope at horizon for ADSEC swing arm wiring and testing • PF Swing Arm Commissioning – Rotator resource competition LBT Q1 2007 Engineering Review

  3. Progress (Q1/2007) SX and DX ADSEC Swing Arms Installed ADSEC wiring, limit switch testing scheduled 2nd and 3rd week of April LBT Q1 2007 Engineering Review

  4. Planning (Q2/2007) • ADSEC Swing Arm Preload • GUI Testing • Prime focus swing arm commissioning? LBT Q1 2007 Engineering Review

  5. LBT Q1 2007 Engineering Review Swing Arms (SWA) Howard

  6. Highlights (Q1/2007) • Installed right secondary swing arm in January • Installed left secondary swing arm in March LBT Q1 2007 Engineering Review

  7. Open Issues • Technical • Repeatability measurement • Vibration measurement • Loose Brace on M3 Swing Arm on 3L • Schedule • Prime Focus Swing Arm Commissioning Plan • Swing Arm Shock Absorbers • Financial • None • Resource • Mountain manpower availability • Chamber lift shortage LBT Q1 2007 Engineering Review

  8. Progress (Q1/2007) • Installed Secondary Swing Arms • Surveyed DX PF SA prior to LBC Red Installation • Wiring of Secondary Swing Arms in Progress LBT Q1 2007 Engineering Review

  9. Planning (Q2/2007) • Come up with a Prime Focus SA Commisioning Plan • Repeatability • Vibration • Deploy/retract speed • AS Swing Arm Preload & Alignment • Primary Mirror Cover Test Fit #3 • Remove SX M3 SA (clean bearings while it is off) LBT Q1 2007 Engineering Review