LBT Q1 2007 Engineering Review

LBT Q1 2007 Engineering Review. DAQ. Housekeeping System Requirements. Interface directly to the Agilent 34970A Absolute accuracy better than 0.5° C Resolution better than 0.05°C Measurement range at least -25°C to +35°C Locations (symmetrical left and right)

Download Presentation

LBT Q1 2007 Engineering Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q1 2007 Engineering Review DAQ

  2. Housekeeping System Requirements • Interface directly to the Agilent 34970A • Absolute accuracy better than 0.5° C • Resolution better than 0.05°C • Measurement range at least -25°C to +35°C • Locations (symmetrical left and right) • C-ring extension, M3 swing arm height, front and rear • C-ring extension, M2 swing arm height, front and rear • Telescope rear counterweights on the C-ring outside LBT Q1 2007 Engineering Review

  3. Housekeeping System Basic Design • RTD (Resistance Temperature Detector) • 4-wire installation LBT Q1 2007 Engineering Review

  4. Highlights (Q1/2007) • Basic design finished • Procured sensors for testing • Installed two test sensors • Surface temperature • Air temperature • Data collection and analysis begun LBT Q1 2007 Engineering Review

  5. LBT Q1 2007 Engineering Review

  6. LBT Q1 2007 Engineering Review

  7. LBT Q1 2007 Engineering Review

  8. LBT Q1 2007 Engineering Review

  9. Open Issues • Technical • Signal noise • Shielding • Sensor placement • Fragile • Avoid blocking access for maintenance LBT Q1 2007 Engineering Review

  10. Open Issues • Schedule • Installation requires telescope access • Financial • None • Resource • Personnel for fabrication and installation LBT Q1 2007 Engineering Review

  11. Progress (Q1/2007) • Completed basic design • Testing • Installed surface temperature sensor • Collected two weeks of data • Installed air temperature sensor • Currently collecting data LBT Q1 2007 Engineering Review

  12. Planning (Q2/2007) • Data Analysis • Procurement of additional sensors • Installation of additional sensors LBT Q1 2007 Engineering Review