An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Petition to Council re Homestead Road/Weaver Dairy Road Extension May 9, 2005

  2. Requests • Seek accident statistics from NCDOT/NCHP • Install traffic light • Add turn lanes • Annex intersection into town • Notify neighbors about petition

  3. Background • Vineyard Square SUP approved 6/25/01 • Project connected Weaver Dairy Road Extension to Homestead Road • Improvements to Homestead were a key issue for council

  4. Background • Manager’s preliminary recommendation called for “exclusive left and right turn lanes” on Homestead • Could be built by NCDOT, developer (Centex) or a third party • Construction was to precede CO

  5. Background • Transportation and Bike & Ped boards supported manager’s recommendation • Developer objected, on cost • Planning Board agreed • Council dropped turn lanes

  6. Background • Final SUP required … • Dedication of half a 90-foot ROW along site’s Homestead frontage • Payment in lieu ($24,000) for a traffic signal

  7. Problem • The lack of a signal or turn lane has created a dangerous situation for eastbound traffic

  8. Problem • Neighbors: Many accidents here • Neighbors: Turn lane is needed • Limited sight lines • Limited bailout space

  9. Concluding points • Council assumed NCDOT would widen Homestead starting in FY05 • NCDOT has not widened and the 2006-12 TIP draft lists Homestead as a “post years” project • Only work has been a NC Moving Ahead! paving that added to the shoulder

  10. Concluding points • Planning staff memo for 5/14/01 public hearing said TIA submitted to that point was incomplete • “We believe that applicant’s Traffic Impact Analysis does not thoroughly address all potential future traffic scenarios for this development.” • Manager’s recommendation thus assumed worst-case impact