Vacuum ComponentsUndulator System SH Lee, J Morgan, and D Walters
Major Components • Vacuum Chamber Support • Bellows • Quadrupole Spool • BFW Support • RFBPM Support • Long Break Spool Chambers • Girder Extensions
Vacuum Chamber Support • Tubular Chamber Support • First Article shipped from ANL 1/13/08, expect arrival at SLAC on 1/23/08 • Expect balance to ship 2/16/08 • Adjustment Mechanism • Expect First Article to ship1/24/08 • Expect final group 1 (35) to ship 2/22/08
Bellows • E7-345050 Flange and Bellows Assy. • Award No: 8A-03419 • Award Date: 01/11/2008 • Supplier: APPLIED ENERGY SYSTEMS INC • Delivery Date: 05/11/2008 Based on the vendor's delivery schedule in the quote, It is expected on 02/16 for 1st article and completion 03/16 • E7-352011 for Beam Tube • Award No: 8A-03623 • Award Date: 01/16/2008 • Supplier: WALCO TOOL & ENGINEERING CORP • Delivery Date: 03/16/2008 It is expected on 02/16 for 1st article and completion 03/16 • Cleaning, baking, and assemble at the APS before sending to SLAC • Best estimate for the completed units 2/25/08 for the First Articles and the balance by 3/25/08
Quadrupole Spools • First Articles are at ANL Aluminum was plated onto parts
Quadrupole Spools Best estimate of shipping (3) First Articles is 1/28/08 Balance to ship 2/21/08
BFW & RFBPM Support • BFW Support • First Article planned to ship on 1/24/08
Long Break Chambers • The requisition for this has just recently been written. Seeking delivery of this to be 8 weeks. • Chambers will have to come to ANL for leak check, clean, and bake.
Girder Extension • The requisition for this has just recently been written. Seeking delivery of this to be 8 weeks.