An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRD ROC Status Material status, Problems, Schedule TRD workshop Cheile Gradistei Romania, 26.9.2005 TRD Workshop Cheile Gradistei 2005 Clemens Adler

  2. Wire • Anode wire: • no major problem reported since March. • In Dubna and Hd: some Anode wire seemed weak (breaking during winding). • 10% of rolls identified as bad. • Recent deliveries looked very good. • Cathode wire: • Some doubts about quality occurring once in a while. 7% of rolls identified as ‘Bad’. • Also ‘good’ rolls display irregular surfaces-> increased danger of premature aging (Malter effect). • Different manufacturer available: will be tested at GSI in the next chamber. • Decision to buy new wire, discard old wire? TRD Workshop Cheile Gradistei 2005 Clemens Adler

  3. TRD Workshop Cheile Gradistei 2005 Clemens Adler

  4. Hardener • Bad batch of hardener: • Production stop for ~5 weeks • Additional delay due to shipment for Dubna/Bucharest • New Hardener tested by Jörg: OK (shear strength, surface conductivity) • Some changed behavior: longer curing time (24h), sticky surfaces already at <40% rel. humidity. • Bucharest: higher surface conductivity, humidity caught in sticky surface? TRD Workshop Cheile Gradistei 2005 Clemens Adler

  5. GSI gain uniformity • Bad uniformity on L5C1 chamber • Most likely bent pad plane panels • Not really understood L4C1 panel glued with weight in the middle Good uniformity TRD Workshop Cheile Gradistei 2005 Clemens Adler

  6. Schedule - Currently estimated end of production: 4/2008 (was: 1/2008 in Feb 2005) - Critical Path: GSI/Bukarest w/o delays (hardener): rate~0.9ch/week →stay with 1 ch/week guideline - Other production sites not critical (even at 0.5 ch/week rate for Hd/F) TRD Workshop Cheile Gradistei 2005 Clemens Adler

  7. Schedule Future Material procurement • With production delays: • No material shortage expected before Autumn 2006 • Fits well with expected date of decision to build 100% (April 06 ?) • Realistic chance to get rest of material in time. TRD Workshop Cheile Gradistei 2005 Clemens Adler

  8. Potential Stones on our way… Back panel: Quality control at Fischer (Manfred Mast): OK Pad planes: Quality control in Hd/F: OK Wire ledges/distance ledge: no problems expected Field cage PCB: no problems expected HV cable: so far only 1 bad batch, new rolls are tested at Hd, OK Signal cables: so far no problems: new order needed soon Glue (Hardener): tested and bought in large quantities L-profiles: to be seen (Choice of material) Radiator: sometimes bad gluing joints, L0C1: carbon laminate came off easily: has to be watched Glue (Epoxy comp.: Aw116, AW106): QA needed Anode wire: changing quality; QA: difficult Cathode wire: changing quality;QA difficult ??? TRD Workshop Cheile Gradistei 2005 Clemens Adler

  9. Chambers for 1st SM • Chambers from Dubna and Bucharest will be shipped in October. • Chambers from GSI should arrive end of October • Chamber test of leak rate +HV after transport. TRD Workshop Cheile Gradistei 2005 Clemens Adler

  10. Conclusions • Chamber production delayed by 3 month (compared to estimate in Feb) • Hardener: open questions? • Cathode wire: change manufacturer, how soon? • Schedule: still acceptable, but cannot afford much more delays TRD Workshop Cheile Gradistei 2005 Clemens Adler