1 / 17

Risk Analysis of Swamp Area at Zürich Airport

Risk Analysis of Swamp Area at Zürich Airport. 1. Background. ICAO SARPs

zudora
Download Presentation

Risk Analysis of Swamp Area at Zürich Airport

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk Analysis of Swamp Area at Zürich Airport

  2. 1. Background • ICAO SARPs • According to ICAO Annex 14, 9.2.2 where an aerodrome is located close to water/swamp areas, or difficult terrain, and where a significant portion of approach or departure operations takes place over these areas, specialist rescue services and fire fighting equipment appropriate to the hazard and risk shall be available • Situation ZRH • Zürich airport does not fulfill the ICAO requirements • A safety assessment/aeronautical study has been conducted (by Ernst Basler + Partner AG) focussing on the following questions: • What is the risk of an aircraft crash or a veer-off into the swampy area between RWY 14/32 and 16/34 at Zürich airport? • Identification of potential mitigation measures (equipment, infrastructure, procedures) • Analysis of the effectiveness of the proposed measures • Cost-effectiveness of measures ACI OSSC Meeting 11.-13. September 2007

  3. Existing was Approved Non-Conformities identified Document background (historical basis) Co-ordinated by FOCA Classification Significant Safety ** assessment Major Safety Case ** Minor Responsibility Airport No ALARP* ? Update ALARP* ? Yes u.a. Cost-benefit considerations No Mitigate Yes Remove Hazard Compliance Checklist Standards and Recommended Practises * ALARP: As low as reasonably practical ** Co-operation with ANSP, if necessary ACI OSSC Meeting 11.-13. September 2007

  4. The Area I Natural reserve !! ACI OSSC Meeting 11.-13. September 2007

  5. The Area II ACI OSSC Meeting 11.-13. September 2007

  6. Difficult Access ACI OSSC Meeting 11.-13. September 2007

  7. System Definition Risk-based Approaches • Hazard identification • Risk anaylsis • Scenarios • Probability • Impact / Damage • Determine Risk • Risk Appraisal • Criteria • Risk Appraisal • Evaluate Measures • Risk Mitigation ACI OSSC Meeting 11.-13. September 2007

  8. Accident Analysis I: Probability • Assumptions • 1980-2005 • A/C >15 pax • 330 accidents (RWY excursions, CFIT, loss of control, with/ without fires) • Within 1250m from Threshold • Within 750m from each RWY edge • Accident rates • 1.7 x 10-7 per take-off movement • 6.4 x 10-7 per landing movement ACI OSSC Meeting 11.-13. September 2007

  9. Accident Analysis II: Impact Willingness-to pay: 10 Mio. CHF per life saved ACI OSSC Meeting 11.-13. September 2007

  10. Collective Risk • R= movements (per year) x accident rate x probability of being in swamp x impact x value per life saved • „Risk equals the expected damage per year for a defined scenario“ ACI OSSC Meeting 11.-13. September 2007

  11. Risk assessment • Probability* • 0.0023 Events / year (re-occurrence period of 440 years). The probability of an accident at ZRH within the swampy area is expected to be 1.7 * 10-8 per movement (approach or take-off). • Risk • 0.012 casualties / year and a monetarized risk of CHF 121'000.-- / year. • * All events within the swampy area at ZRH (3.8% of all excursions, veer offs) including a fire and at least a partial hull loss ACI OSSC Meeting 11.-13. September 2007

  12. Thorough evaluation of 32 measures • Evaluation of effects of measure on: • improved accessability for crash fire tenders • improved accessability for other F&R means • evacuation of passengers/crew • transportation of passengers/crew out of crash site ACI OSSC Meeting 11.-13. September 2007

  13. Risk mitigation measures • Selected Measures • Ungraveld road into parts of the swampy area • Footpath into the swampy area • Special vehicule to transport water/exinguishing agents • Special vehicule to transport water hoses • Transportable foldable mat to enable access for crash tenders • Rafts for adjacent pond ACI OSSC Meeting 11.-13. September 2007

  14. Results I • Effectivenes of measures between -0.1% and -20% reduction of probability (outbrake of fire) and impact (confining fire, fast rescue of pax) • risk reduction between CHF 5‘000.- and CHF 13.- per year • cost of measures between CHF 470‘000.- and CHF 3‘700.- per year ACI OSSC Meeting 11.-13. September 2007

  15. Results II Meaning: - Annual cost of this safety measure is 286 CHF - The annual risk reduction is 1 CHF ACI OSSC Meeting 11.-13. September 2007

  16. Results III • None of the identified measures has a reasonable cost-benefit ratio measures ineffective • According to the ALARP* principle, the risks are acceptable • Swiss Civil Aviation Authority (FOCA) has accepted the study as a basis for showing compliance with the corresponding ICAO SARP • FOCA has requested Unique (Zurich airport) to take the following actions – gather refined data on ground resistance and accessability of area – examine/evaluate accessability of area – perform F&R exercises in the area • *As Low As Reasonably Practicable ACI OSSC Meeting 11.-13. September 2007

  17. Thank you for you attention ! ACI OSSC Meeting 11.-13. September 2007