Woodrow Wilson Bridge Reconstruction Test Embankments for Route 1 Interchange. June 4, 2001. VDOT. WWB TEST EMBANKMENTS. Recommended by FHWA Limited Scope/Budget ($2 Million) Limited Time for Completion (1/00 to 2/01). VDOT. OBJECTIVES FOR TEST EMBANKMENTS. Assess Rates of Consolidation

Download Presentation

Woodrow Wilson Bridge Reconstruction Test Embankments for Route 1 Interchange

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Woodrow Wilson Bridge ReconstructionTest Embankments for Route 1 Interchange June 4, 2001 VDOT

  2. WWB TEST EMBANKMENTS • Recommended by FHWA • Limited Scope/Budget ($2 Million) • Limited Time for Completion (1/00 to 2/01) VDOT

  3. OBJECTIVES FOR TEST EMBANKMENTS • Assess Rates of Consolidation • Verify Predicted Settlements • Optimize PV Drain Spacings • Determine Mix Design Parameters • Verify Design Assumptions • Verify Constructability • Refine/Develop Specifications VDOT

  4. P.V. DRAIN (PVD)TEST EMBANKMENT • 8’ of Granular Fill over 10’-12’ of Soft Alluvial/ Organic Clays (A1) over Terrace Sand/Gravel • 90’ x 45’ Embankment With Vertical MSE Face • Embankment 14’ +/- Above Original Ground • 6’ of Surcharge; 2’ Drainage (Sand) Blanket • 9,000 Tons of Select Material VDOT

  5. PVD INSTRUMENTATION • 12 Settlement Plates • 3 Observation Wells • 4 Vibrating Wire Piezometers • 3 Inclinometers • 2 Magnetic Extensometers • 16 Settlement Pins; 8 PK Nails VDOT

  6. PVD INSTRUMENTATION • Clustered for Constructability • Time for Installation included in Contract Specifications • Installation/Monitoring by VDOT (Owner) • Penalties (Time/Money) Assessed for Contractor Damage to Instruments VDOT

  7. DESIGN INFLUENCE OF PVD TEST EMBANKMENT • 5’ Spacing instead of 4’ Spacing • 6-Month Consolidation Stages • Estimated Direct Savings of $650,000 • Contractual “Lessons Learnt” (Pre-drilling; Pay quantities; Production Rates; Constructability) VDOT

  8. DEEP MIX METHODS (DMM)TEST EMBANKMENT • “Wet” and “Dry” Mix Columns (Single Augers) • “Wet” Mix Panels (Triple Augers) • 8’ of Granular Fill over 32’ of Very Soft Organic/Alluvial Clays (A1) over Terrace Sand/Gravel • Organic Contents 1%-15% VDOT

  9. DMM TEST EMBANKMENT

  10. DMM INSTRUMENTATION • 8 Settlement Plates • 1 Observation Well; 2 Piezometers • 4 Vibrating Wire Piezometers • 7 Inclinometers (6 Vert.; 1 Horiz.) • 2 Magnetic Extensometers • 8 Pressure Cells • 11 Settlement Pins • 6 Thermistors VDOT

  11. DESIGN INFLUENCE OF DMM TEST EMBANKMENT • Specified “Wet” Mix Exclusively • 2’ Construction Platform (Sand) • Contractual “Lessons Learnt” (Acceptance Criteria; Mix Design Criteria; Production Rates; Constructability) VDOT