140 likes | 268 Views
This update details the ongoing construction progress of the El Cerrito High School Stadium, including site plans and work completed by general contractor Wright Contracting, chief architect WLC Architects, and construction manager Hector De Leon. The project, with a contract amount of $13,438,000, commenced on January 27, 2014, and is set for completion on September 27, 2015. Key activities include retaining wall construction, site grading, and underground utilities installation, with a change order totaling $10,285.
E N D
WCCUSD Bond ProgramConstruction Update El Cerrito High School Stadium 07/15/2014
El Cerrito High SchoolStadium Conceptual Design
General Contractor Wright Contracting • Architect of Record WLC Architects • Construction Manager Hector De Leon • Project Engineer Maria Zupo • Inspector of Record Kris Gilbert El Cerrito High SchoolStadiumProject Team
El Cerrito High SchoolStadium Site Plan
Contract Amount $13,438,000 • Notice of Award 11/21/13 • Notice to Proceed 01/27/14 • Duration 608 days • Completion Date 09/27/15 • Change Order $10,285.00 (0.07%) El Cerrito High SchoolStadiumGeneral Information
Site retaining walls at Ashbury and Colusa • Fence piers at Colusa • Building retaining walls and foundations • Site grading and compaction • Underground utilities El Cerrito High SchoolStadiumProgress Update
El Cerrito High SchoolStadium Ashbury Avenue Elevation