This update presents the latest developments in the Long Beach Community College District's construction projects as of July 26, 2010. The agenda includes current and upcoming projects such as the LAC Building A Retrofit, LAC Parking Structure, and PCC Multi-Disciplinary Academic Building. Key highlights include anticipated completion dates, significant expansions, and energy efficiency improvements. Engaging the community and providing transparency are critical goals as we enhance educational facilities and infrastructure.
E N D
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District July 26, 2010 EDUCATE ENGAGE EMPOWER
Agenda • Current & Upcoming Construction Projects • LAC Building A, Student Services Retrofit • LAC Parking Structure • LAC Building O Complex • LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project • LAC Building I (Bookstore) • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Building CC Retrofit • District Wide – Electronic Signage Plan • LAC South Walkway Extension • LAC Building P FPP • Q & A
Current and UpcomingConstruction Projects LAC Building A – Student Services Retrofit Measure E 2008 • Awaiting DSA Final approval on Structural portion • Adds 6,500 Sq. Ft. to existing building • Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. • Estimated start of construction Fall 2010
Current and UpcomingConstruction Projects LAC Parking Structure – Measure E 2008 • Spaces for 900 Vehicles • Construction started Summer of 2010 • Anticipated end of Construction Fall 2011
Current and UpcomingConstruction Projects LAC Building O Complex – Measure E 2008 • Two structures totaling 87,000 square feet • Construction of Building O1 began April 2010 • Anticipated completion October 2010
Current and UpcomingConstruction Projects LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 • Project to be completed in a phased construction schedule • Total annual estimated savings of 1.5 million Kwh • Project started Fall 2009; currently working on phase 5, 5A, & 6A • Landscaping upgrades to be implemented in conjunction with infrastructure project phasing • Majority of existing building HVAC systems to be upgraded and connected to the Central Plant • Exterior lighting and controls upgrades in progress • Anticipated end of construction Winter 2011
Current and UpcomingConstruction Projects LAC Building I - Measure E 2008 • Received Final DSA approval • Adds additional 4,000 square feet to existing building • Architecture to match LAC Mediterranean Theme • Going to bid in August • Construction scheduled for Fall 2010 • Bookstore Swing Space relocation beginning Summer 2010
Current and UpcomingConstruction Projects PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002 • Received Final State (DOF) approval • NTP to be issued on 7/29/10 • Install portables for swing space Summer 2010 • Anticipated start of MDAB construction Fall 2010 • Project to be completed in two phases
Current and UpcomingConstruction Projects PCC Building CC Retrofit - Measure E 2008 • Currently in DSA for plan check (Structural) • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space to be located on PCC Campus (Bldg. GG) • To be completed concurrently with MDAB project phase 1 • Anticipated end of construction 2012
Current and UpcomingConstruction Projects District Wide – Electronic Signage Plan Measure E 2008 • District Wide Signage Plan complete for LAC & PCC • Daktronics digital signs currently in fabrication • Anticipated construction completion of Marquee Signs Fall 2010
Liberal Arts Campus Site Plan l i b e r a l a r t s
Pacific Coast Campus Site Plan p a c i f i c c o a s t
QUESTIONS& ANSWERS EDUCATE ENGAGE EMPOWER