130 likes | 237 Views
Follow the progress of the Pinole Valley High School Interim Campus construction project, including concrete pouring, paving, fencing installation, and more. Stay informed about the ongoing developments and upcoming completion date.
E N D
WCCUSD Bond ProgramConstruction Update Pinole Valley High School Interim Campus 08/12/2014
General Contractor JUV, Inc. • Architect of Record WLC Architects • Construction Managers SGI Construction Management • Eddie Law • Marc Alojepan • Verna Van • Inspector of Record Mark Eriksen Pinole Valley High School Interim CampusProject Team
Contract Amount $5,530,000 • Notice of Award 03/19/14 • Notice to Proceed 04/07/14 • Duration 130 days • Completion Date 08/15/14 Pinole Valley High School Interim CampusProject Team
Concrete poured at all retaining walls and walkway (final pour on-going) • AC paving (paving at front entrance area now and ramps) • Installation of fencing and gates – on-going • Power to all portables, final yesterday • Data line pull, termination, testing and labeling on-going • Fire alarm testing today • Installation of picnic tables and benches – on-going • Fire and domestic line chlorination (today), flush and bacteriological test • Installation of signage today • Kitchen health inspection conditional operational permit – Effective 8/8/2014 • Administration move and set-up – on-going • Teacher return/un-pack and classroom set-up – on-going • Final clean and AC striping – on-going Pinole Valley High School Interim CampusProject Status