1 / 18

Signing Performance Measures Report 2005 Data

Signing Performance Measures Report 2005 Data. Policy Replace signs near end of useful life Measure 1) Percent of signs replaced annually to meet a 12 year cycle 2) Percent of signs over 12 years old Target Replace 8 percent annually to achieve 12 year life cycle.

luna
Download Presentation

Signing Performance Measures Report 2005 Data

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Signing Performance Measures Report2005 Data District Engineer Presentation

  2. Policy Replace signs near end of useful life Measure 1) Percent of signs replaced annually to meet a 12 year cycle 2) Percent of signs over 12 years old Target Replace 8 percent annually to achieve 12 year life cycle Signing Policy, Measures & Target District Engineer Presentation

  3. District Engineer Presentation

  4. District Engineer Presentation

  5. Total Number of Signs(Signs, Markers and Delineators) District Engineer Presentation

  6. Note: D7 is up to date District Engineer Presentation

  7. Note: D7 is up to date District Engineer Presentation

  8. District Engineer Presentation

  9. District Engineer Presentation

  10. 19,851 signs replaced statewide in 2005 => 60 percent of annual target D1, D4 and D6 were close to meeting the 8% target for this year D7 is 100% and D8 is 96% up to date. D2, D3 and Metro still struggling to meet 8 percent annual target due to lack of staff; increasing number of new signs/replacement of damaged/vandalized signs D1, D4 and D8 exceeded target in 2003 or 2004 due to sign replacement contracts supplementing Mn/DOT sign crews 2.4 %decrease in statewide measure from 2004 to 2005 Summary District Engineer Presentation

  11. Analysis • Longer life cycle of new prismatic sheeting (VIP and DG3 15+ years) compared to HI sheeting (12 years) • Statewide Sign Management System Implementation over next two years • Cost to maintain signing asset will continue to rise (both material and labor costs) • Number of new/vandalized signs has stabilized in 2005 • 1% annual growth of new signs statewide • Gap between target and what can be accomplished within budget and staff constraints will grow District Engineer Presentation

  12. Financial Impact - HSOP $3.8 million needed annually for next four years to eliminate the backlog, replace old interstate signs and keep pace with system growth • $1.4 million (materials and installation costs) to bring 9% statewide backlog of aging signs up to12 year replacement cycle • $1 million for interstate sign replacement in Districts 1, 3 and 6 which have several segments of interstate highways with signs 15 to 20 years old ($3.9 Million has been program for 2007 – 2010) • $1.4 million (materials and installation costs) for 1% annual growth in sign system statewide District Engineer Presentation

  13. Continue to use the percentage of signs replaced to meet 12 year cycle as one performance measure Continue to use the percentage of signs over 12 years old to measure “Overall Sign System Condition” Implement sign management system in Metro, D6 and D8 by June 2007 (Phase 1) Implement sign management system in remaining districts by June 2008 (Phase 2) Continue to use capital program to replace larger interstate signs (D1, D3 and D6 have all scheduled projects totaling $3.9 Million in ’07-’10) Signing Recommendation District Engineer Presentation

  14. HSOP Recommendation • (pp. 3-69 – 3-71) • Signing Implementation Strategies (section D) “Mn/DOT should continue to pursue the development of an automated sign inventory and management system to track the repair and maintenance of signing activities… . Without a sign management system, it becomes more difficult to manage the system efficiently and ensure that signs are being replaced before the end of their useful life.” District Engineer Presentation

  15. SMS Benefits from D7 • Reduced SAMMS inventory by 80% • Can now order only what’s needed • Can reference a history of what has been used • Ability to project an actual Mn/DOT cost for signing activities • Collected information ads in producing an accurate Work Plans • Maintain history of duration and frequency for each activity • Ability to estimate cost of predictable activities District Engineer Presentation

  16. SMS Benefits (Continued) • Ability to produce accurate signing plans and contracts including accurate cost estimates • Ability to predict cost of proposed signing changes • Extra trips to site for verification reduced when repair or replacement needed • Recorded detailed work history provides ability to: • Identify problems with site, location, and hardware • Record repair costs for restitution • Achieve maximum life from signs • Answer specific questions about field inventory • Determine best business practices District Engineer Presentation

  17. SMS Project Status • Selected SignTrack as Mn/DOT standard SMS software • Statewide license for up to 100 users and one year of maintenance has been purchased. ($163,000) • Yearly maintenance $281 per used license (to be paid by district/office operating budgets starting in FY 2008) • Central server has been purchased by OIT • Kay McDonald from OIT will be co-project manager with a mobility from district maintenance. District Engineer Presentation

  18. Project Teams • Sign Business Practices • Define procedures and activities • Define fields, pick lists, libraries • Define relation to WMS (work orders, work plans and LEMO) • Traffic Business Practices • Review signing contracts and SignCAD • Develop library definitions • Traffic Work Orders (TWO) • State Aid, Fed Aid and Municipal agreement projects • Reporting • Mapping Issues • Microstation, Arcview and Basemap • Mile Markers, Reference Posts and XY Coordinates • Service Level Agreements District Engineer Presentation