Join us for the Mu2e Working Group Meeting on June 16, 2010, from 1:00 to 2:30 PM in the Snake Pit. Agenda includes project updates, cosmic ray veto discussion, schedule development, project controls, and more. Don't miss the opportunity to be informed and involved in the project progress.
E N D
Mu2e Working Group Meeting June16, 2010 1:00– 2:30 PM Snake Pit
Agenda • Project Update (including requirements documents development, CDR development and resource/staffing needs [Ron Ray] • Cosmic Ray Veto [Craig Dukes] • Schedule Development and Change in Project Controls [Dean Hoffer] • Project Timeline [Dean and All] • Next Meeting • Action Items 16-Jun-2010 Mu2e WGM
Project Controls and Schedule Development • Change in Project Controls Support • Larry Kirkpatrick – Lead • Dave Leeb • Bob Aprile (limited) • Evaluating current status of existing schedule and analyzing WBS • Discussion with Ron on analysis results • Project Controls meet with L2s 16-Jun-2010 Mu2e WGM
Next Meeting • Next Meeting 13-Jul, 1:00 – 2:30 PM • Next L2 Presentation? 16-Jun-2010 Mu2e WGM
Action Items a) Get L2 Manager for calorimeter in place. – Ron Ray b) Get resources required for CD-1 activities into P6. Begin adding relationships and developing BOEs – L2s/Project Controls c) Understand and document the magnitude of the heat shield problem – Rick Coleman d) Get moving on FE Electronics – Ron Ray 16-Jun-2010 Mu2e WGM