LBNE Working Group Meeting

LBNE Working Group Meeting. June 27, 2012 3:30– 4:30 PM (CT) Snake Pit. Agenda. Project Report [Jim Strait/Elaine McCluskey ] LBNE Reconfiguration Results of Tuesday’s meeting with DOE Discussion on planning Director’s CD-1 Review [Dean Hoffer] Next Meeting [Dean Hoffer].

kaz
Download Presentation

LBNE Working Group Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBNE Working Group Meeting June 27, 2012 3:30– 4:30 PM (CT) Snake Pit

  2. Agenda • Project Report [Jim Strait/Elaine McCluskey] • LBNE Reconfiguration • Results of Tuesday’s meeting with DOE • Discussion on planning Director’s CD-1 Review [Dean Hoffer] • Next Meeting [Dean Hoffer] 27-Jun-2012 LBNE WGM

  3. Director’s CD-1 Review Preps • Tentative Schedule: Week of September 17 • Confirming Key Management Availability • Scope Focus: • Cost/Schedule/Management (this includes ES&H and Quality) • Follow-up to implementation of Applicable Recommendations from Director’s Review in March • Duration – estimate at 2 – 2 ½ (need agenda to finalize) • Charge – started working on • Agenda – work on draft after Charge is drafted 27-Jun-2012 LBNE WGM

  4. Director’s CD-1 Review Preps (continued) • Will be 4 Breakout Sessions • Beamline • Detector • Civil Facilities • Project Management • Reserve Meeting Rooms • Most Rooms Available • May need to move MINOS Collaboration Meeting out of One West on 20-Sept • Establish Review Committee Team • Start drafting list and request participation after Charge is finalized with draft agenda 27-Jun-2012 LBNE WGM

  5. Director’s CD-1 Review Preps (continued) • OPMO Review Website – Will create when finalize review date • LBNE Review Website • LBNE to have review documents posted by the end of day on Monday, 3-Sept. (Labor Day) • This includes all the CD-1 related documents (i.e. PEP, PMP, Schedules, BOEs, MOU, links to internal design reviews, etc.) • Drafts of all Plenary and Breakout talks are to be posted by that Monday also • Additions/Updates to the documents/talks can be made after that Monday, but need to indicated on webpage of the change and the date of that change 27-Jun-2012 LBNE WGM

  6. DOE CD-1 Review • DOE CD-1 Review consistent of two reviews in one. • Independent Project Review (IPR) • Performed by Office of Project Assessment (OPA) • Independent Cost Review (ICR) • Performed by Office of Engineering and Construction Management (OECM) • Schedule October 30 • Duration - 3 or 4 Day Review • Review Documentation would need to be posted by the end of day Monday, October 15 (this includes presentations for plenary and breakouts – can be draft). 3 ½ weeks after end of Director’s Review 27-Jun-2012 LBNE WGM

  7. DOE CD-1 Review (continued) • Rooms – Current conflict with 3 rooms because of Project X Collaboration Meeting (have call into Steve Holmes to discuss) • Working with Steve Meador from OPA on review details • Potential call early next week (w/ Steve Meador and Mike Procario) 27-Jun-2012 LBNE WGM

  8. Independent Cost Review • OECM Reviewers are part of the OPA Review Team (usually part of Cost and Schedule Subcommittee) • Some documentation requested earlier than then required posting date (Based on Mu2e Review) • WBS and Dictionary • Cost Book • Lifecycle Costs • Alternative Analysis • OECM gave us a Typical ICR Checklist (document link out on WGM webpage) • OECM Reviewers gave to project areas of WBS that they would concentrate on during review (about 2 weeks ahead of review) 27-Jun-2012 LBNE WGM

  9. Next Meeting • Ongoing every two weeks • Next Meeting will be on Tuesday 17-July from 3:00 – 4:00 PM (CT) and then every two weeks after until review 27-Jun-2012 LBNE WGM