TRD Chamber production issues

TRD Chamber production issues. Planning and Hd Status. 9xL1C1 finished 2xL1C1 being wired 3xL1C0 3xL2C0 1xL1C0 not usable? (Badly glued Padplane: maybe repair possible). Manpower: 2 technicians (Chamber building) 1 student (pad plane QA, chamber production)

gafna
Download Presentation

TRD Chamber production issues

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRD Chamber production issues Planning and Hd Status TRD Collaboration Meeting GSI Clemens Adler

  2. 9xL1C1 finished 2xL1C1 being wired 3xL1C0 3xL2C0 1xL1C0 not usable? (Badly glued Padplane: maybe repair possible) Manpower: 2 technicians (Chamber building) 1 student (pad plane QA, chamber production) 3 Technicians (Front- L-profiles production) 1Technician from Bukarest (L-profiles production) Production rate: ~1Chamber/week (if no problems apear) Heidelberg Status TRD Collaboration Meeting GSI Clemens Adler

  3. Layer 6 scenario: (decision this weekend) finish L6C0 material and include in next Dubna transport (in 3 weeks): ->1st Supermodule Chambers: May 1st (+transport from Dubna/Bukarest) decision in 3 weeks: additional transport to Dubna, ->1st Supermodule Ch: July 1st (+transport time) Layer 0 scenario: (decision this weekend) L0C0,L0C1 Material at Hd: May,1 L0C0 material in Dubna: June 15th ->1st Supermodule Chambers: July 1st (+transport) (better have a transport in Sept./Okt.?) (Assuming no Quality Problems) Schedule TRD Collaboration Meeting GSI Clemens Adler

  4. Dubna: Chamber Transport Dates Supermodule assembly August: Supermodule assembly November: or built 1 L0C0 chamber at Hd TRD Collaboration Meeting GSI Clemens Adler

  5. Bukarest Schedule • No further transport needed this year from point of view of Supermodule assembly. TRD Collaboration Meeting GSI Clemens Adler

  6. Current distribution of types: Dubna: L1-6C0 Bukarest:L2C1, L3C1 GSI: L5C1, L6C1 HD: L1C1(part), L4C1 Ffm: L1C1 (rest), +? L1C1: produced in Hd until May, in Frankfurt starting July,1st- Oct ? Proposed change: Dubna: L0-5C0 Bukarest: L2C1, L3C1 GSI: L4C1, L5C1 HD: L1C1(part), L0C1 Ffm: L1C1(rest), +? L0 Implications for other Sites TRD Collaboration Meeting GSI Clemens Adler

  7. Estimated SM production dates(just from Chamber point of view) • Transport delays not taken into acount • - Assumption: Money for 100% detector material is available Spring 2006 • All estimates based on 1 Chamber/week average production rate • Suggestion to use as a ‚base plan‘ until different production rates are observed TRD Collaboration Meeting GSI Clemens Adler

  8. Cashflow? • In current plan: • Frankfurt is finished with 50% L1C1 in October 2005 • Heidelberg is finished with 50% L0C1 in February 2006 • GSI,Bukarest finish L2C1,L3C1,L4C1,L5C1 June 2006 Consequence: Frankurt/Heidelberg have to produce L2C1/L3C/L4C1/L5C1 TRD Collaboration Meeting GSI Clemens Adler

  9. Hd: 7 L1C0 6 L2C0 24 L1C1 28 L0C1 Dubna: 12 L0C0 7 L1C0 6 L2C0 10 L3C0 8 L4C0 12 L5C0 Bukarest: 2 L1C0 2 L2C0 20 L2C1 20 L3C1 GSI: 20 L4C1 24 L5C1 Fankfurt: 20 L1C1 Chambers until End of 2005 TRD Collaboration Meeting GSI Clemens Adler