An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CLS Control SystemProgress Report Elder Matias Canadian Light Source University of Saskatchewan Saskatoon Saskatchewan

  2. EPICS Environment • EPICS 3.14 • Development: RedHat Linux 7.2 • Servers: RedHat Linux 7.2 • OPI: RedHat Linux 7.2 MS-Windows 2000 • IOC: RTEMS RedHat Linux 7.2 • PLC: MODICON Momentum S7/300 or S7/400

  3. Linac – Complete • Old CAMAC and NeXT hardware replaced. • Modulator control and most vacuum control converted to MODICON Momentum PLC hardware • IOC connection: MODBUS over Ethernet • Old Power supplies upgraded with single board computers running IOC software. • NI FieldPoint used for slow parameters • IOC Connection: RS-232

  4. Booster • Nearly complete • Vacuum control using MODICON Momentum • Diagnostics using VME hardware and PowerEdge Server/Linux • RF Control using S7/300 hardware • link to EPICS still under development • Magnet Power Supplies controlled over RS232

  5. Storage Ring, Beamlines • System Design and Implementation has started • Based on similar technologies and design strategies to linac and booster • Motor control on beamlines will be based on the CLS standard motor control hardware

  6. Control Room Software • The Canadian Nuclear Safety Commission requires CLS to conduct detailed task analysis, this activity is driving our operator screen layouts • EDM has been selected for operator consoles under Linux • Standard EPICS applications (strip tool, alarm handler etc.) are being used • Augmented with some customizations or custom applications • Some specialised applications running under MS-Windows 2000

  7. Services • HVAC and Cooling Towers with Invensys DMS complete, integration with EPICS postponed • Secondary Cooling System - MODICON Momentum and NI FieldPoint – complete • Power Metering/Transformer Control – under development • Cryogenics Plant - S7/400 - under development

  8. 2. Transfer Line & Booster ring 1. E-gun and Linear Accelerator 3. Storage ring 4. Beamline & end station

  9. Existing Linear Accelerator