An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q3 2007 Engineering Review DYB

  2. Highlights (Q3/2007) • Currently in Commissioning Phase • Vast majority of hardware and electronics installed. • Bypass valves and level sensors still need to be installed. • Pipe insulation work in progress • System test in progress. • Software tests are in progress. • Current Completion Date is November 30th, 2007 (Slip from Nov 16th due to late valves and sensors). LBT Q3 2007 Engineering Review

  3. Open Issues • Technical • Installation of bypass valves, level sensors, and vent lines in cable drape still pending. • Schedule • Level sensors in customs should release next week. • Bypass valve delivery due 2nd week of November. • Financial • None • Resource • Will need electrical techs to wire up level sensors. • Need mechanical tech help for installing level sensors and vent hose in cable drape. LBT Q3 2007 Engineering Review

  4. Progress (Q3/2007) • Procurement • Mechanical Components ( Planned Sep) (Completed except for pump bypass valves, due in 2nd week of November) • Pipe Insulation will be last item procured. (Completed in October) • Electrical Components (Planned July/Completed in August except for level sensors.) • Software Development • First cut of PLC Code (Planned July/Completed in August) • Bench Test (Planned July – Aug/Completed in September) • Changes made based on testing (Planned Aug/In progress) • Installation • Tank Installation (Planned July/Completed in July) • Electrical Installation (Planned Aug/(Completed in October) • Will need to replace z-axis flowmeter cable with longer one due 2nd week of Nov. • Piping • Select vendor/Issue Contract (Planned July) (Completed in August) • Begin Piping Installation (Sep 10) (Started on time and completed ahead of time) • Piping Insulation (In progress 60% complete/planned to be completed in Oct) LBT Q3 2007 Engineering Review

  5. Progress Cont. (Q3/2007) Flowmeter Transmitters PLC Rack 24 V Box 480 V Box Y Vent Tank -Y Tank LBT Q3 2007 Engineering Review

  6. Progress Cont. (Q3/2007) Flowmeter Motorized Valve Pump Modified RH -Z-Tank Insulated Pipe LBT Q3 2007 Engineering Review

  7. Planning (Q4/2007) • Procurement • Bypass Valves, Level Sensors, Longer and Flowmeter Cable (2nd week Nov.) • Installation • Insulation (Oct) • Bypass Valves, Level Sensors, and vent lines through cable wrap (Nov) • Commissioning • Software Tests (Oct ) • Commission Level Sensors and Calibrate Overflow Sensors (Nov) • Acceptance Tests and Handover (Nov) • Documentation (Nov) LBT Q3 2007 Engineering Review