An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ISUAL Development Status and Schedule H. Heetderks

  2. ISUAL Imager Status • ETU Design and Fabrication are Complete • ETU Testing 70% Complete • All electrical functions fully checked out • Motor Controller, Wheel Position Sensor, and Filter Mechanism all working • Photo cathode power supply and switch • Heater and Thermal monitor circuits • Camera Electronics fully checked out • All Operating Modes have been verified • High Voltage Supplies conformally coated to Flight standards • Tested to full voltage at ambient pressure • All Printed Circuit Board layouts have been up dated to current Flight status • All Machined and Purchased Parts for Flight Unit are in House • This includes delivery of all Barr Filters • New Thermostats and Heaters on order for thermal control upgrade • New Tapers on order for improved optics performance • New TEC machined parts being made to improve CCD cooling • Flight Printed Circuit Boards will be etched later in ETU test program NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  3. ISUAL Spectrophotometer Status • ETU unit with two Photometer Channels has been completed and taken to Kitt Peak, Colorado for testing on actual Sprites • System worked as planned except for unexpected Cosmic Ray contamination • Problem appears to be exacerbated by scintillations in the sapphire window of the PM tube • This type of contamination interferes with use of the photometer as a trigger source • We have developed an electronic technique for rejecting the cosmic ray events • We are also investigating the use of glass tubes • A revised pre-Amplifier design is currently being tested • This is expected to be a relatively simple change • The primary modification is to the Actel on the IDC board in the AEP • All Machined and Purchased Parts for Flight Unit are in House • Exception: EMR Photomultiplier with Magnesium Fluoride window for Channel 2 (UV) • All Barr Filters have been delivered • New Thermostats and Heaters on order for thermal control upgrade • Flight Printed Circuit Board changes have not yet been made to the layout NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  4. Associated Electronics Package Status • ETU Low Voltage Power Supply Board fabrication is complete • Board is fully functional with all unit testing complete • ETU Power Controller Board fabrication is complete • Board is fully functional with all unit testing complete • ETU Data Processing Unit Board fabrication is complete • Board functionality is 50% complete and unit testing is 40% complete • ETU Mass Memory Board fabrication is complete • Board functionality is 100% complete and unit testing is 50% complete • Completion of testing is contingent on delivery of AP and DCM ETU’s • ETU Data Compression Module Board fabrication is complete • Board functionality is 10% complete and unit testing is 5% complete • ETU Instrument Data Controller Board is currently in design stage • This board contains the interfaces to the Array Photometer and the Spectrophotometer • AP interface design is now complete • SP interface design is currently being refined to deal with AP cosmic ray contamination problem • All Machined and Purchased Parts for Flight Unit are in House • This includes delivery of all electronic parts including rad hard IC’s • Flight Printed Circuit Boards will be etched later in ETU test program NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  5. ISUAL Software Status • Commands and Engineering Functions and Telemetry are up and Running • Science Data Collection Software is complete and under test • Overall, Instrument Software is about 80% complete • All GSE functions are fully functional • Overall, GSE Software is about 90% complete NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  6. ISUAL Array Photometer Contracting Status • Contract between UCB and the Japanese company AD Advanced Technology is in place • AP development is fully under way NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  7. ISUAL Schedule Highlights • ETU Assembly will Complete by 1 Feb, 2002 • Release of Circuit Boards for Flight Unit Etch 15 Feb, 2002 • Fully Assembled Flight Unit 1 May, 2002 • Flight Unit Functional Testing Complete 15 July, 2002 • Flight Unit Environmental Testing Complete 15 Sep, 2002 NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  8. ISUAL Summary Schedule at TRR NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  9. ISUAL Summary Schedule at CDR NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  10. ISUAL Manpower Plan at TRR NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks