1 / 10

ISUAL Development Status and Schedule

ISUAL Development Status and Schedule. H. Heetderks. ISUAL Imager Status. Mechanical Design Complete All Drawings in Configuration Control Bidding complete and parts due at UCB on 20 July, 2001 Lens, Intensifier, CCD, and F.O. Taper are in House

eron
Download Presentation

ISUAL Development Status and Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ISUAL Development Status and Schedule H. Heetderks

  2. ISUAL Imager Status • Mechanical Design Complete • All Drawings in Configuration Control • Bidding complete and parts due at UCB on 20 July, 2001 • Lens, Intensifier, CCD, and F.O. Taper are in House • Barr Filters originally scheduled for June delivery, now 15 July • Camera Electronics (7 Circuit Boards) • All Schematics Released • ETU Boards Etched and loaded • Analog operation and one digital mode is checked out • Needs revised Actel to complete checkout • Flight Stepper Motors and Heat Pipe are on Order • All Electronic Parts are Received or on Order • High Voltage Power Supply Design and Layout complete and ETU Boards have been Etched and partially loaded • Control Circuits PCB design is complete and ETU board is in Etch NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  3. ISUAL Spectrophotometer Status • Mechanical Drawing Package is Complete • Mechanical Parts Fabrication is Complete • ETU and Flight Lenses and ETU Photomultiplier Tubes are in House • ETU PM Tube potting in process • Filters originally Scheduled for June Delivery, now July • Flight PM Tubes Scheduled for August Delivery • ETU Printed Circuit Board (has PM pre-amps) is assembled and tested • High Voltage Power Supply ETU assembly is complete and checkout is in process NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  4. ISUAL System Associated Electronics Package Status • ETU and Flight Mechanical Parts Fabrication is complete • ETU Power System Fabrication and Checkout are nearly Complete • ETU Data Processing Board is assembled and in checkout • ETU Mass Memory Board is assembled and in checkout • NCKU Supplied Data Compression Board set for July Preliminary Integration • Electronic parts are Under Control • All parts are on order; Most of these are in house • Lagging and late addition parts are being carefully tracked and no problems are expected NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  5. ISUAL Software Status • Commands and Engineering Functions and Telemetry are up and Running • Testing of Science Data Collection and Transmission is in process NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  6. ISUAL Array Photometer Contracting Status • UCB has been unable to get Tohoku under contract • Current strategy is to contract directly with the Japanese company AD Advanced Technology • Tohoku has developed a Statement of Work and and Instrument Specification for the AP, and UCB as sent a formal Request for Proposal to AD Advanced Technology NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  7. ISUAL Schedule Highlights • ETU Assembly will Complete by 1 Sep, 2001 • Release of Circuit Boards for Flight Unit Etch 1 Nov, 2001 • Fully Assembled Flight Unit 1 Feb, 2002 • Flight Unit Functional Testing Complete 1 Apr, 2002 • Flight Unit Environmental Testing Complete 1 June, 2002 NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  8. ISUAL Summary Schedule at CDR NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  9. ISUAL Summary Schedule at IFR NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

  10. ISUAL Manpower Plan at CDR NCKU UCB Tohoku ISUAL Status & Schedule H. Heetderks

More Related