Status and Schedule. M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors status Finances Schedule and Milestones. UXC. Experimental Cavern UXC55 More than 50% complete UXC55 ready July 04. USC.

asa
Download Presentation

Status and Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors status Finances Schedule and Milestones

  2. UXC Experimental Cavern UXC55 More than 50% complete UXC55 ready July 04

  3. USC Service Cavern USC55 More than 50% complete USC55 ready March 04

  4. Swiveling Platform (Korea) Assembly finished at Pt. 5 Swiveling Platform

  5. Swiveling test in 2002 A counterweight will be installed to simulate the equivalent weight and momentum due to the cantilevered 250 t of the Cold Mass

  6. Status of Conductor Each length is 2650m long

  7. Winding Prototype 4 layers winding using spare length of 2.65km – progressing well Full diameter 6m 1/4 length ~0.6m

  8. CB-2 mandrel ready Coil is made of 5 submodules CB-2, CB-1, CB0, CB+1, CB+2 Mandrel for CB-2 is finished ~6 months late – problem with supply of special elements in high strength alloy for mandrels, plates and flanges. CB-2 completed end 02 CB+2 completed end 03

  9. Compressors for Cryogenics at point 5

  10. Tracker Outer Barrel Module Hybrid with ST sensors APV • 50% of Si Strip Tracker budget committed • Si modules from the Milestone 200 produced in different production centers • Start of Si module production shifted from June 2002to Nov. 2002 due to hybrid optimization (safer design and cost).

  11. Production Hybrids First 4 received, flex cable ok !!! 20 + 20 ordered, delivery ½ May All mechanical test up to now are ok Specifications ready by 25/5 Going to tender asap

  12. Outer barrel rod fully equipped for system test First small sub-system (outer barrel ‘rod’) equipped with modules

  13. Beam Pipe EDR and Pixel installation EDR went well and pixel installation was proven to be compatible with our expectations.

  14. Crystals and Photodetectors All 138 ovens at BTCP modified to grow large boules Offers in hand for endcap xtals APDs Expected rate of 5000 APDs/month reached. 25k out of 130k APDs delivered VPTs First 500 production VPTs delivered

  15. ECAL: Mechanics Module assembly Endcap ‘Supercrystal’ Assembly of modules for first supermodule (SM1) started in CERN and Rome. EE EDR mid-2002

  16. Supermodule Assembly Assemble a few ‘bare’ SMs in 2002

  17. ECAL Electronics CMS and LHCC Reviews in 2001 revealed major cost overruns in electronics Last RRB: Double speed of optical links – half cost of links – BUT insufficient Action - Mar 02:Alter electronics architecture to contain costs – generate L1 trigger primitive (S25 xtals) on-detector rather than off-detector – reduce links and off detector electronics by factor ~ 10. FPPA: Final submission May02 Electronics team reorganised, synergy between ECAL, Tracker & Preshower electronics TDR TP 91000 Data and Control Links 800 Off-detector Trig/DAQ Boards 12000 Data and Control Links 120 Off-detector Trig/DAQ Boards

  18. 2002 2004 2006 2003 2005 EB Fabrication Integration and Test EE & SE Fabrication Integration and Test Feasibility Prototypes System Tests Detailed Design Procurement Installation EB + EB - EE - EE + Test Beam ECAL Planning Goal: Apr 07 - ECAL complete and commissioned Advance the detailed test (also system test) of 1st SM to mid-2003 (final analog electronics + emulated FPGA digital part) EB electronics mounted in 2004/2005 – calibrate at least 9 SMs in 2004 EE and SE mounted in 2005/2006, calibrate 1 Dee in 2006 Electronics Schedule

  19. Evolution of CMS Data Acquisition • New modular design of Event Builder - Break into a number of functionally identical, parallel, smaller DAQ systems • A 64x64 system is feasible today • Submit DAQ TDR end-02

  20. High Level Trigger Lvl-1 trigger in construction phase now HLT running in processor farm – immense amount of data generated – exercising remote sites Detailed analysis leads to < 400> ms/event (on a “PIII @ 700 MHz box”) • Maximum flexibility: full event data available; • using offline software (very important to understand HLT performance) • In terms of “2007” CPU units, this is 3*1.5 years away. CPU needs should be within reach A 50kHz system at startup will need ~ 2500 CPU’s N(CPU) = (0.4 sec x 50000 sec-1)/(2*2*2)= 20000/8 = 2500 CPU time/evt L1-rate Moore’s law At (staged) startup: 50kHz @ Lvl-1 and 80Hz to storage Discovery physics “safe”. SM physics: ~ resource-driven High luminosity: in DAQ TDR at end-2002

  21. Construction: Commitment Profile Apr 02 RRB By end of 2002 ~70% of the available funds will have been committed. 62.7 MCHF of additional funds need to be committed soon in order to have a complete initial low luminosity detector in 2007.

  22. ~20 MCHF Staging/Savings ? After RRB13 the Director of Research requested CMS to prepare plans for the case where 20 MCHF of the shortfall is not covered (with respect to the RRB13 shortfall of 67.9 MCHF) BUT with the hope of getting it later. Staging/Saving already applied for 1st Physics Run ~5 MCHF HCAL: Reduce no. of longitudinal samplings 2.0 MCHF ME1/1a: Reduce no. of electronics channels 1.5 MCHF ME4/1: re-stage electronics 1.5 MCHF Additional Staging Considered for 1st Physics Run ~8.5 MCHF TRIDAS: Start with 50% of DAQ Capacity 8.0 MCHF Infrastructure: SCX Cooling and Ventilation Plant 0.5 MCHF Additional Saving Under Technical Evaluation ~5 MCHF LV Supplies: Use 400Hz, 400V system 5.0 MCHF Decision in June 2002. TOTAL Staging/Savings ~ 18.5 MCHF

  23. Additional Collaborators Serbia Corner Pieces Magnet approved in Mar CMS Week 400 kCHF protocol agreement Milan, INFN ECAL approved in Mar CMS Week Naples, INFN RPCs approved in Mar CMS Week Brazil YE4+ farmYE4 funded (500 kCHF),application in 2002 Ireland ECAL electr.?, farm Visited CERN 18-19 Feb Expect application in mid-02 Mexico Silicon Tracker Expect application soon NZ farm+Pixels Applic. received, Pres. in June Visit at CERN S. Thompson Thailand ME electronics boards in progress US-NP (HI) TriDAS, farm Successful workshop in MIT 8.02 Proposal submitted to DoE March 15 0.9 MCHF already in Financial Plan.

  24. High Luminosity Upgrades 10. Items (upgrades) for high luminosity ~ 19 MCHF 10.1 ME4/2 mechanics and electronics 9.2 10.2 ME4/1 electronics 1.5 10.3 ME4/1 assembly in PNPI 0.5 10.4 Restore ME1/1a electronics 1.5 10.5 Neutron Shielding (extra) 1.0 10.6 3rd Forward Pixel Layer ~2.5 10.7 5th endcap RPC layer ~2.0 10.8 Extra Installation Costs ~1.0 The decision to build many of these items will only be taken after inspection of the first physics data. This upgrade cost comes on top of the 62.7 MCHF shortfall. A plan for the funding of the upgrade will have to be worked out in due time. Basic ingredients are new collaborators or upgrade plans by funding agencies willing to upgrade items in which they have been working on.

  25. April RRB (RRB14) Outcome M&O MoU accepted, proceed with signatures M&O cat A 2002 Budget accepted (1 MCHF with sharing according to nb of PhDs). No request for in kind contributions in 2002. M&O Cat B: Must work out a way to share costs (by Oct RRB) C&I costs accepted (positive report by scrutiny group). C&I profile peaks in 2003. Cash flow? 50% of C&I is manpower. CMS Financial Plan well received. Expect ~ 54 MCHF additional funds for a shortfall of 62.7 MCHF. Next step - Reach an agreement with Agencies by end June 02 on likely availability of funds (firm, less firm promisies), amounts and time profiles. Then prepare Financial Plan for Oct RRB (also discuss during LHCC CMS CR in Oct02)

  26. Expectations for additional funding at RRB14 Guideline Expect Guideline Expect Austria 600. 600. Belgium 870. 300. Brazil 500. 500. Bulgaria 106. CERN 13500. 13500. China 700. 700. Croatia 49. 49. Cyprus 106. Estonia 16. Finland 870. 870. France CEA 1000. 660. France IN2P3 4000. 2000. Germany 2703. 2703. Greece 880. Hungary 58. India 774. 300. Iran 500. 500. Italy 12900. 12900 req. Korea 458. Pakistan 428. Poland 528. Portugal 352. 352. RDMS 2250. 2250. Serbia 400. 400. Spain 1350. 1350. Switzerland Taipei 410. Turkey 58. UK 1530. 1530. USA 15000. 12800. TOTAL 62896. 54264.

  27. V33 Draft Schedule: Extended Surface Phase Additional costs part of C & I Objectives: channel test of HV/LV burn-in of electronics flushing gas readout test of 10% of subdet (MB,ME, RB etc) vertical slice tests with test-beam DAQ & prototype final DAQ

  28. v33 Draft Schedule • A new planning v33 is in preparation for the next LHCC comprehensive review. • Objective: Complete CMS (except pixels and ME4) for 1 April 2007 • UX and US area ready (+12 months shift, now firm date) Jul 04. • Install floor plates and shielding in UX area Nov 04- Apr 05 • Magnet test on surface (+9 months shift) Jan 05- Apr 05 • Start lowering CMS May 05 • ECAL Barrel (EB) ready for installation (+ 4 months) Jul 05 • Start EB installation + cabling (3 months float) Nov 05 • Tracker ready for installation Oct 05 • Start Tracker installation + cabling (3 months float) Feb 06 • EE+ (ECAL endcap positive z-side) calibration in SPS beam Apr 06- Sep 06 • Start EE+ installation Nov 06 • Start EE- installation Jan 07 • CMS closed ready Apr 07

  29. Conclusion Magnet: Yoke finished. Conductor and winding well advanced. 1st coil delivered end 02 with 6 months delay. Not critical: HCAL, Endcap Muons : construction on schedule and well advanced. Problems are being encountered but are also being overcome. To watch Production rate of DTs and RPCs – need to watch production rate Start of mass assembly of Si modules (Q4 2002) ECAL:Redesign of electronics chain. Very tight schedule. Draft v33 CMS Schedule Magnet test on surface Jan 05- Apr 05. Start lowering detector in May 05. CMS closed ready for 1’st beam 1st April 07. CMS construction is proceeding at speed. A low luminosity detector can be ready for physics in 2007. The low luminosity detector is the complete CMS detector, except the 4th forward muon station (ME4) and the 3rd forward pixel layer.