1 / 7

All Experimenters’ Meeting

March 4, 2013. All Experimenters’ Meeting. Photo by Martin Murphy. Shutdown 2012. Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning and studies

zuri
Download Presentation

All Experimenters’ Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. March4, 2013 All Experimenters’ Meeting Photo by Martin Murphy

  2. Shutdown 2012 Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning and studies TeV & Muon Rings – Partially available for tours with approval and appropriate training

  3. Power Outages - Unplanned • Feeder 46B • Tuesday, January 29th • Isolated fault (Between F4 & P71) • Repairs pending

  4. MSS Bypass Project - Completed • Booster • High Intensity Lab (HIL) • Neutrino Service Building 7 (NS7) • Proton Service Building 1 (PS1) • Neutrino Service Building 1 (NS1)

  5. Power Outages – MSS Bypass Project • MS2 Oil Switch • February 25th for ~ 2 weeks • Will be running house power off a generator (Until 3/8) • Impacts – MS2 Service Building and Adjacent Enclosure (M02) • MS1 Oil Switch • March 11thfor ~ 2 weeks (3/11 or 3/12 0800-1000) • Will be running house power off a generator • Impacts – MS1 Service Building and Adjacent Enclosure (M01)

  6. Power Outages – Planned • WH8FC – Wilson Hall 8th Floor Fiber Central • Sunday, March 10 from 0600 – 1200 • Although this is a very local power outage, its effects are widespread and all networking in Wilson Hall will be offline including: • Finance backup systems (5th floor) • Remote Operating Center (ROC) • Com Center • 12th floor control room • Service Desk • Cardkey Access – works but no changes or updates • DOE Office • CUB • Minos/IF Underground networking • FESS/WH building monitoring (16th floor) Several redundant Kerberos, Windows and Fermi domain controllers will also be down when WH8FC is powered off.

  7. Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html ANU - http://www-cons/ Proton Source -http://www-ad.fnal.gov/proton/protonsched/shutdown2012.html

More Related