1 / 33

Central MA Transmission Study

Central MA Transmission Study. Long-term Needs and Solutions Presentation to: NEPOOL Reliability Committee January 18, 2005. Central MA Infrastructure Study. Study Initiated in 2001 Identified Short-term and Long-term Upgrades to ensure reliability of service

veata
Download Presentation

Central MA Transmission Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Central MA Transmission Study Long-term Needs and Solutions Presentation to: NEPOOL Reliability Committee January 18, 2005

  2. Central MA Infrastructure Study • Study Initiated in 2001 • Identified Short-term and Long-term Upgrades to ensure reliability of service • Study area covers region bounded by: • Sandy Pond (NE) • Pratts Jct (NW) • Carpenter Hill (SW) • Northboro Rd (SE)

  3. Geographic Location of Central MA

  4. Short-term Upgrades • 18.4 applications approved in February 2002 • 63 MVAr Capacitor Bank at Millbury • 54 MVAr Capacitor Bank at Northboro Road • Also adjusted taps on Ayer 115-69 kV transformers • In-service for Summer 2002

  5. Long-term Upgrades • 18.4 applications approved in April 2004 • Install 69 kV circuit breaker at Woodside • Install 2nd 115-69 kV transformer at Wachusett • Replace Millbury T1 and T2 115-69 kV transformers • Install two additional 115-69 kV transformers at Pratts Junction, replace 69 kV circuit breakers, and transfer one-half Prospect Street load • Wachusett 345-115-69 kV substation • Reconductor 115 kV lines O-141N, P-142, W-175 • Reconductor 69 kV lines M-39, N-40 • Replace 115 kV circuit breaker at Rolfe Ave • Upgrade W. Boylston protection systems • Replace W-23E 69 kV line disconnect

  6. Long-term Upgrades • Transmission Cost Allocation presentation made to NEPOOL RC in April and May 2004 • Uncertainty regarding GIS costs for Wachusett substation resulted in deferral of application • Additional engineering has been performed for the three 345-115 kV substation sites • Firm bids received for the GIS

  7. Long-term Needs in Central MA • Needs identified in three main areas • Millbury • 115-69 kV transformer loading • 115 kV voltage • Sandy Pond • 345-115 kV transformer loading • Ayer • 115-69 kV transformer loading • 69 kV voltage

  8. Existing Problems 4. Ayer 69 kV Area voltage drops below 0.9 pu for K-137 + L-138W DCT contingency 3. Ayer T4 & T6 Overload for loss of each other 2. Sandy Pd T1 & T2 overload for loss of each other 5. Shrewsbury 69 kV Breaker overdutied 1. Millbury T1 & T2 Overload for loss of each other

  9. Review of Recommended Solutions • Millbury: • Replace existing T1 and T2 with larger transformers • Ayer: • Transfer Prospect Street from 69 kV line V-22E to U-21S; install two (2) 115-69 kV transformers at Pratts Jct and replace eight (8) 69 kV breakers • Wachusett: • Install two (2) 345-115 kV transformers and 345 kV and 115 kV GIS at existing Wachusett substation and associated upgrades

  10. Millbury Alternatives • Recommendation: • Replace existing T1 and T2 with larger transformers ($1.5 M) • Alternatives: • Add fourth 115-69 kV transformer into dedicated bus position ($3.8 M) • Add fourth 115-69 kV transformer tapped off Q-143, relocate I-35 ($2.1 M) • Convert 69 kV line X-24 to 115 kV to unload existing transformers ($14.9 M)

  11. Millbury Substation 56 MVA 56 MVA Replace T1 and T2 (50 MVA) w/ 56 MVA Transformers Millbury – Replace Two (2) 115-69 kV Autotransformers

  12. Millbury Solution • The recommendation is based on: • Lowest cost • Simpler construction compared to adding a 4th transformer • Existing Millbury transformers can be relocated to Wachusett substation

  13. Ayer Alternatives • Recommendation: • Transfer Prospect Street from 69 kV line V-22E to U-21S; install two (2) 115-69 kV transformers at Pratts Jct and replace eight (8) 69 kV breakers ($2.47 M) • Alternatives: • Install (2) 115-69 kV transformers at Ayer ($4.5 M) • Convert 69 kV line V-22 to 115 kV to unload existing transformers ($13.7 M)

  14. Transfer ½ of Prospect St Load from V-22E to U-21S 56 MVA 56 MVA Two Additional 115-69 kV Autos at PJ Pratts Jct Sub – Install Two (2) Additional 115-69 kV Autotransformers

  15. Ayer Solution • The recommendation is based on: • Lowest cost • Simpler construction at Pratts Junction compared to Ayer

  16. Sandy Pond 345-115 kV Transformers • Loss of either T1 or T2 overloads the remaining transformer • Considered installation of new 345-115 kV transformers at: • Sandy Pond • Tewksbury • Pratts Junction • Millbury • Wachusett • Quinsigamond Junction

  17. Sandy Pond Alternatives • Preliminary analysis indicated: • Sandy Pond and Tewksbury do not support Central MA voltage • Millbury and Tewksbury not effective at unloading Sandy Pond transformers • Pratts Junction, Wachusett, and Quinsigamond Junction locations meet both needs

  18. Evaluation of Alternatives • The Pratts Junction, Wachusett, and Quinsigamond Junction sites were fully evaluated to provide: • A list of associated upgrades based on thermal and voltage analysis • Study grade estimates for all upgrades associated with each option

  19. Recommended Sandy Pond Solution • Initial recommendation made based on air-insulated substation estimates for Wachusett, Pratts Junction, and Quinsigamond Junction • Wachusett alternative recommended based on: • Lowest cost • Wachusett PW = $32.2 M • Pratts Junction PW = $32.3 M • Quinsigamond Junction PW = $36.1 M (based on ±25% study grade estimates) • Better system performance compared to Pratts Junction option • Less environmental impact than Pratts Junction option (N-40/W-23 conversion) or Quinsigamond Junction (new substation)

  20. Transient Stability Analysis • Analysis conducted for the preferred alternative • West Boylston substation becomes a bulk power system substation • High-Speed pilot protection required for P-142 line from Wachusett to West Boylston • Incremental Cost = $0.880 M • Did not change recommendation

  21. Wachusett Construction Issues • Construction Grade estimate developed for the preferred alternative • Identified wetland issues that limit use of existing Wachusett site • Encroachment on intermittent stream and associated wetlands that are tributaries to Wachusett Reservoir • Wetland replication not permitted if alternatives exist • Gas Insulated Substation required

  22. Review of Alternatives • Additional engineering required to evaluate alternative sites to obtain MA DTE, NEPOOL, and National Grid approval • Additional engineering identified issues with Pratts Junction and Quinsigamond Junction sites

  23. Pratts Junction Site • Site preparation work required for air insulated substation would encroach on perennial stream • Impacts to estimated habitat and priority habitat for species protected by MA Endangered Species Act • Gas Insulated Substation requires filling an environmentally critical area • High likelihood this location would not be approved if alternatives exist

  24. Quinsigamond Junction Site • Air insulated substation would impact perennial stream and associated wetlands • Gas Insulated Substation required • Research identified former use of substation site as oil company tank farm • Records not available to assess additional cost if soil contamination is identified

  25. Wachusett GIS Layout

  26. Wachusett Alternative - Costs • Woodside 69 kV Breaker 2004 0.700 M • Wachusett 2nd 115-69 kV Xfmr 2006 2.530 M • Wachusett 345-115-69 kV 2006 41.959 M • O-141/P-142 Protection Upgrades 2006 0.440 M • Reconductor O-141N 2006 1.500 M • Reconductor P-142N 2006 0.125 M • Reconductor M-39 2006 1.000 M • Reconductor N-40 2006 1.181 M • Replace Rolfe Ave Breaker 2006 0.366 M • Reconductor W-175 2006 0.475 M • W. Boylston Upgrades 2006 0.440 M • Replace W-23E Disconnect 2006 0.020 M

  27. Pratts Jct Alternative - Costs • Woodside 69 kV Breaker 2004 0.700 M • Pratts Jct Substation 345-115 kV 2006 25.700 M • Pratts Jct Substation 115-69 kV 2006 4.885 M • Replace Pratts J 115 kV Breakers 2006 3.225 M • Replace Pratts J 69 kV Breakers 2006 0.840 M • Reconductor N-40 2006 1.180 M • Reconductor O-141N 2006 0.750 M • Replace W-23E Disconnect 2006 0.020 M • Convert N-40/W-23 to 115 kV 2012 18.300 M

  28. Quinsigamond Jct Alternative - Costs • Woodside 69 kV Breaker 2004 0.700 M • Quinsigamond Jct Sub 2006 41.484 M • Wachusett 115-69 kV Upgrades 2006 5.475 M • Replace O-141S Terminal Equip. 2006 0.500 M • Reconductor M-39 2006 1.000 M • Reconductor N-40 2006 1.180 M • Replace Rolfe Avenue Breaker 2006 0.366 M • Reconductor W-175 2006 0.475 M • Replace Pratts J 69 kV Breakers 2006 0.840 M • Replace W-23E Disconnect 2008 0.020 M

  29. Cost Comparison Alternative Total Cost Present Worth Pratts Jct $55.623 M $50.886 M* Quinsigamond Jct $52.041 M $52.041 M Wachusett $54.696 M $54.696 M * 2012 cost to convert 69 kV lines N-40/W-23 to 115 kV discounted to 2006

  30. Technical Comparison • All three alternatives provide adequate voltage support and unload Sandy Pond transformers • Wachusett and Quinsigamond Junction provide the most reliable system • Most balanced system power flows • Better line out (n-1) performance • Less sensitive to future system changes (e.g. load forecast)

  31. Environmental Comparison • All three sites require Gas Insulated Substations • Pratts Junction: • Requires filling an environmentally sensitive area • Requires conversion of 69 kV lines to 115 kV • Quinsigamond Junction • Development of a new site • Potential soil contamination issues from past use as tank farm • Wachusett • Existing site • Gas Insulated Substation addresses environmental concerns

  32. Operational Comparison • Similar cutover plans for 345 kV substations • Two outages of four days to relocate lines and cutover substation • Pratts Junction requires outage of N-40/W-23 lines in 2012 for conversion to 115 kV • Impacts to voltage support in the Northboro Road area

  33. Recommendation • The Wachusett alternative is recommended • Additional 7% cost compared to Pratts Junction is offset by: • Better technical performance • Less environmental impact • Less operational impact during construction • Less uncertainty regarding cost and schedule • Additional 5% cost compared to Quinsigamond Junction offset by: • Less environmental impact • Less uncertainty regarding cost and schedule

More Related