1 / 18

Central MA Transmission Upgrades: TCA Revision

Central MA Transmission Upgrades: TCA Revision. NEPOOL Reliability Committee June 16, 2009. Central MA Upgrades - History . 18.4 applications approved in April 2004 Install 69 kV circuit breaker at Woodside Replace Millbury T1 and T2 115-69 kV transformers

rex
Download Presentation

Central MA Transmission Upgrades: TCA Revision

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Central MA Transmission Upgrades:TCA Revision NEPOOL Reliability Committee June 16, 2009

  2. Central MA Upgrades - History 18.4 applications approved in April 2004 • Install 69 kV circuit breaker at Woodside • Replace Millbury T1 and T2 115-69 kV transformers • Install two additional 115-69 kV transformers at Pratts Junction, replace 69 kV circuit breakers, and transfer one-half Prospect Street load • Wachusett 345-115-69 kV substation • Reconductor 115 kV lines O-141N, P-142, W-175 • Reconductor 69 kV lines M-39, N-40 • Replace 115 kV circuit breaker at Rolfe Ave • Upgrade W. Boylston protection systems • Replace W-23E 69 kV line disconnect

  3. Central MA Upgrades – TCA History • Initial TCA (15.5) – RC Action deferred in June 2004 Based on conceptual cost estimations, the initial TCA application submitted to RC in May 2004. • Revisions 0 & 1 – Approved in January 2005 Captured higher costs due to GIS instead of the originally scoped air insulated substation. Wetlands restrictions drove the design to GIS. • Revision 2 – Submitted now to capture “As-Built” costs Wachusett Sub commissioned March 2007. Punch List items extended into 2008 ($4.8M). Actual Costs tracking delayed.

  4. TCA & Project Timeline 2004 2005 2005 2006 2007 2008 2009 18.4 Approved Multi 15.5/TCA $43.4 M TCA - Rev 0 (Consolidated) $54.7 M TCA - Rev 1 Approved $54.7 M TCA - Rev 2 “As Built” $69.7 M Project Construction extended into 2008 - invoice processing/punch list closeout items, - accounting retrieval/summary time – into 2009

  5. Millbury Substation Upgrades Scope: Replace existing T1 and T2 (115-69 kV) with larger transformers Millbury upgrades completed in 2005 Cost Estimate: 1.50 M Actual Cost: 1.17 M Favorable construction resulting in reduced cost

  6. W-175 115 kV Line Upgrade Scope: Reconductor 115 kV line. Line upgrades completed in 2004 Cost estimate: .474 M Actual cost: .858 M Reason for cost increase • Additional work to increase clearances to comply with NESC, • Static wire severely deteriorated requiring replacement, • Operational requirements and use of external resources at increased cost.

  7. O-141N & P-142 115 kV Line Upgrades Scope: Reconductor each 115kV line. Line upgrades completed in 2005 Cost estimate: 1.625 M Actual cost: 1.509 M Reason for cost decrease – favorable construction Minor design changes tended to increase costs as did operational requirements and use of external resources but were offset by favorable construction.

  8. O-141N & P-142 115 kV Line Protection Upgrades Scope: Upgrade protection on line/breaker at Wachusett. Line upgrades completed in 2007 Cost estimate: 0.440 M Actual cost: 1.357 M Reason for cost increase • All 115 kV equipment (Ngrid & Municipal) • Control building extension to accommodate additional equipment.

  9. M-39 & N-40 69 kV Line Upgrades Scope: Reconductor each 69kV line. Line upgrades completed in 2004 Cost estimate: 2.181 M Actual cost: 5.737 M Reason for cost increase • Property rights issues prevented original planned pole replacements/intermediate pole installations. Existing lattice towers instead reinforced, • Additional work to comply with NESC, • Static wire severely deteriorated requiring replacement, • Bird guards added to design, • Operational requirements and use of external resources at increased cost.

  10. Pratt’s Junction Upgrades Scope: Install two additional 115-69kV transformers & replace eight circuit breakers. Pratt’s Jct. upgrades completed in 2005 Cost estimate: 2.46 M Actual cost: 2.95 M Reason for cost increase • Temporary bus connections dictated by operational requirements • Restricted line outage windows causing overtime costs • Additional bus upgrade due to capacity, conductor strain & condition

  11. Wachusett Upgrades Additions to 115-69 kV and new 345-115 kV substation: • Wachusett 2nd 115-69 kV Xfmr completed in 2007 Cost estimate (rev.1): 2.53 M Actual cost: 3.63 M • Wachusett 345-115-69 kV completed in 2007 Cost estimate: 41.96 M Actual cost: 48.54 M • Original Cost Est. – non-GIS (total) 26.50 M (prior to bids being available) Reasons for cost increase • Turn key Project Costs (Rev #1) based on unsigned contracts, • Cost increases uncovered during detailed engineering design, • Contractual increases incurred, • Complexity of construction coordination involving multi-sites, scope, • AFUDC increase - Commissioning 4 month delay (relay & control cabinet delivery), • Increased material cost (see the next slide), • labor and other costs increase due to outage window constraints, • Increased contract vs. in-house crew costs (+25%)

  12. Wachusett Cost vs. Handy-Whitman Industry Cost Index Note: Handy-Whitman Index data taken from The Handy-Whitman Index of Public Utility Construction Costs report dated July, 2008 - Table E-1 “Total Transmission Plant” cost category.

  13. Breakdown of Actual Project Costs Other - includes AFDUC (3.3 M), Contractors (5.5 M), Miscellaneous (4.1 M) items

  14. Other Central MA Upgrades In Svc Estimate Actual • Woodside 69 kV 2004 0.700 M 2.953 M • Rolfe Ave Breaker 2005 0.366 M 0.402 M • W. Boylston Protection Upgrades 2007 0.440 M 0.877 M • Replace W-23E Disconnect 2004 0.020 M 0.108 M Reasons for cost increases • Scope creep – Inclusion of other than originally designed improvements added later in the preliminary engineering stage, • (e.g. protection systems at W. Boylston, structure, and foundation work). • Utilization of crude study grade cost estimations in the original application, • Operational outage considerations during construction (extra cost & temporary work), and • Changing material and labor market.

  15. Overall Cost Summary (2004 Estimates vs. Actual) In Svc Estimate Actual • Woodside 69 kV Breaker 2004 0.700 M 2.953 M • Wachusett 2nd 115-69 kV Xfmr 2007 2.530 M 3.634 M • Wachusett 345-115-69 kV 2007 41.959 M 48.542 M • O-141/P-142 Protection Upgrades 2007 0.440 M 1.357 M • Reconductor O-141N 2004 1.500 M 1.224 M • Reconductor P-142N 2005 0.125 M 0.285 M • Reconductor M-39 2004 1.000 M 3.227 M • Reconductor N-40 2004 1.181 M 2.510 M • Replace Rolfe Ave Breaker 2005 0.366 M 0.402 M • Reconductor W-175 2004 0.475 M 0.858 M • W. Boylston Upgrades 2007 0.440 M 0.877 M • Replace W-23E Disconnect 2004 0.020 M 0.108 M • Millbury T1 & T2 2005 1.500 M 1.173 M • Pratt’s Jct. Transf & Bkr Changes 2005 2.460 M 2.953 M Total: $54.696 M $69.748 M ($15.1 M Diff)

  16. Actual Costs – As Built • As Built costs exceed January 2005 TCA – Rev.1 values by ~27% ($15.1 M) • Requires TCA revision (> 10%) • Total “As Built” PTF cost: $69.7M (vs. $54.7M estimated in TCA – Rev.1) • Higher cost in general due to: • Scope of construction, • Required design changes, • Operational considerations during construction, and • Changing material and labor market.

  17. Transmission Cost Allocation • Construction now fully complete • Seeking Reliability Committee Approval of increased PTF construction costs actually incurred • Increased Amount: $15.1 M (actual dollars spent)

  18. Questions?