1 / 36

Central MA Transmission Study

Central MA Transmission Study. Long-term Needs and Solutions. Central MA Infrastructure Study. Study Initiated in 2001 Identified Short-term and Long-term Upgrades to ensure reliability of service Study area covers region bounded by: Sandy Pond (NE) Pratts Jct (NW) Carpenter Hill (SW)

mala
Download Presentation

Central MA Transmission Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Central MA Transmission Study Long-term Needs and Solutions

  2. Central MA Infrastructure Study • Study Initiated in 2001 • Identified Short-term and Long-term Upgrades to ensure reliability of service • Study area covers region bounded by: • Sandy Pond (NE) • Pratts Jct (NW) • Carpenter Hill (SW) • Northboro Rd (SE)

  3. Geographic Location of Central MA

  4. Short-term Upgrades • 18.4 applications approved in February 2002 • 63 MVAr Capacitor Bank at Millbury • 54 MVAr Capacitor Bank at Northboro Road • Also adjusted taps on Ayer 115-69 kV transformers • In-service for Summer 2002

  5. Long-term Needs in Central MA • Needs identified in three main areas • Millbury • 115-69 kV transformer loading • 115 kV voltage • Sandy Pond • 345-115 kV transformer loading • Ayer • 115-69 kV transformer loading • 69 kV voltage

  6. Existing Problems 4. Ayer 69 kV Area voltage drops below 0.9 pu for K-137 + L-138W DCT contingency 3. Ayer T4 & T6 Overload for loss of each other 2. Sandy Pd T1 & T2 overload for loss of each other 5. Shrewsbury 69 kV Breaker overdutied 1. Millbury T1 & T2 Overload for loss of each other

  7. Millbury 115-69 kV Transformers • Loss of either T1 or T2 overloads the remaining small transformer

  8. Recommended Solution to Millbury T1 and T2 Overload Millbury Station – Replace T1 and T2 (115-69 kV) w/ Larger Transformers Cost: $1.5M In-Service Year: 2004

  9. Millbury Substation 56 MVA 56 MVA Replace T1 and T2 (50 MVA) w/ 56 MVA Transformers Millbury – Replace Two (2) 115-69 kV Autotransformers

  10. Millbury Alternatives • Recommendation: • Replace existing T1 and T2 with larger transformers ($1.5M) • Alternatives: • Add fourth 115-69 kV transformer into dedicated bus position ($3.8 M) • Add fourth 115-69 kV transformer tapped off Q-143, relocate I-35 ($2.1 M) • Convert 69 kV line X-24 to 115 kV to unload existing transformers ($14.9 M)

  11. Millbury Solution • The recommendation is based on: • Lowest cost • Simpler construction compared to adding a 4th transformer • Less permitting risk than 69 kV line conversion to 115 kV • Existing Millbury transformers can be relocated to Wachusett substation

  12. Ayer 115-69 kV Transformers • Loss of either T1 or T2 overloads the remaining transformer

  13. Recommended Solution to Ayer T4 & T6 Overload Transfer 69 kV Load from Ayer to Pratts Jct, and Install two additional 115-69 kV transformers at Pratts Jct Cost: $1.4M In-Service Year: 2004

  14. Transfer ½ of Prospect St Load from V-22E to U-21S 56 MVA 56 MVA Two Additional 115-69 kV Autos at PJ Pratts Jct Sub – Install Two (2) Additional 115-69 kV Autotransformers

  15. Ayer Alternatives • Recommendation: • Transfer Prospect Street from 69 kV line V-22E to U-21S; install two (2) 115-69 kV transformers at Pratts Jct and replace eight (8) 69 kV breakers ($2.46 M) • Alternatives: • Install (2) 115-69 kV transformers at Ayer ($4.5 M) • Convert 69 kV line V-22 to 115 kV to unload existing transformers ($13.7 M)

  16. Ayer Solution • The recommendation is based on: • Lowest cost • Simpler construction at Pratts Junction compared to Ayer • Less permitting risk than 69 kV line conversion to 115 kV

  17. Sandy Pond 345-115 kV Transformers • Loss of either T1 or T2 overloads the remaining transformer • Considered installation of new 345-115 kV transformers at: • Sandy Pond • Tewksbury • Pratts Junction • Millbury • Wachusett • Quinsigamond Junction

  18. Sandy Pond Alternatives • Preliminary analysis indicates: • Tewksbury location • not effective at unloading Sandy Pond transformers • does not support Central MA voltage • Millbury location • not effective at unloading Sandy Pond transformers • Sandy Pond 3rd transformer • does not support Central MA voltage • design challenges to prevent loss of two transformers for a breaker failure contingency • Pratts Junction, Wachusett, and Quinsigamond Junction locations • off-load Sandy Pond transformers • support Central MA voltage • these alternatives identified for further analysis

  19. Sandy Pond 345-115 kV Transformers • The Pratts Junction, Wachusett, and Quinsigamond Junction sites were fully evaluated to provide: • A list of associated upgrades based on thermal and voltage analysis • Study grade estimates for all upgrades associated with each option

  20. Sandy Pond Alternatives • Install two (2) 345-115 kV transformers at existing Pratts Junction substation and associated upgrades • Install two (2) 345-115 kV transformers at existing Wachusett substation and associated upgrades • Install two (2) 345-115 kV transformers at new Quinsigamond Junction substation and associated upgrades

  21. Pratts Jct Alternative - Costs • Woodside 69 kV Breaker 2004 0.700 M • Pratts Jct Substation 345-115 kV 2006 10.400 M • Pratts Jct Substation 115-69 kV 2006 4.390 M • Replace Pratts J 115 kV Breakers 2006 1.628 M • Replace Pratts J 69 kV Breakers 2006 0.840 M • Reconductor N-40 2006 1.180 M • Reconductor O-141N 2008 0.750 M • Replace W-23E Disconnect 2008 0.020 M • Pratts Jct Substation 345 kV 2010 2.700 M • Convert N-40/W-23 to 115 kV 2012 18.300 M

  22. Wachusett Alternative - Costs • Woodside 69 kV Breaker 2004 0.700 M • Wachusett 345-115 Substation 2006 25.750 M • Wachusett 115-69 kV 2006 2.530 M • Reconductor O-141N 2006 1.500 M • Reconductor M-39 2006 1.000 M • Reconductor N-40 2006 1.000 M • Replace Rolfe Ave Breaker 2006 0.600 M • Reconductor W-175 2006 0.475 M • W. Boylston Upgrades 2006 0.670 M • Replace W-23E Disconnect 2008 0.020 M • Reconductor P-142N 2008 0.175 M

  23. Quinsigamond Jct Alternative - Costs • Woodside 69 kV Breaker 2004 0.700 M • Quinsigamond Jct Sub 2006 27.700 M • Wachusett 115-69 kV Upgrades 2006 4.400 M • Replace O-141S Terminal Equip. 2006 0.500 M • Reconductor M-39 2006 1.180 M • Replace Rolfe Avenue Breaker 2006 0.366 M • Reconductor W-175 2006 0.475 M • Replace Pratts J 69 kV Breakers 2006 0.840 M • Reconductor N-40 2006 1.180 M • Replace W-23E Disconnect 2008 0.020 M

  24. Recommended Solution to: Sandy Pd T1 and T2 OverloadLow Voltage in Central MA Wachusett Station – Install two new 345-115 kV Transformers (448 MVA) Cost: $25.75M In-Service Year: 2006

  25. Install 345-115 kV Transformers and Substation at Wachusett Sandy Pd 314N 343N Replace Breakers Pratts Jct P-142N 448 MVA 50 MVA O-141N M-39 B-54 G G G G G G G G G G Wachusett 115 kV 69 kV G 345 kV G G G G 448 MVA G G G G 50 MVA A-53 P-142 O-141 Greendale Boylston Millbury Wachusett – Install Two 345-115 kV Autotransformers (448 MVA)

  26. Associated Thermal and Voltage Upgrades Replace all 69 kV breakers at Pratts Jct for Short Ckt Duty. Reconductor N-40 & M-39 w/ 795 ACSR Reconductor P-142 [Wachusett – W Boylston] w/ 1113 ACSR in 2008 Reconductor O-141N [Quinsigimond Jct – Nashua St] w/ 636 ACSS Replace Rolfe Ave 115 kV Breaker

  27. Preferred Sandy Pond Solution • The Wachusett alternative was identified as the preferred alternative based on: • Lowest cost • Better system performance compared to Pratts Junction option • Less permitting risk than Pratts Junction option (W-23 conversion) or Quinsigamond Junction (new substation)

  28. Transient Stability Analysis • Analysis conducted for the preferred alternative • West Boylston substation becomes a bulk power system substation • High-Speed pilot protection required for P-142 line from Wachusett to West Boylston • Incremental Cost = $0.890 M • Does not change recommendation

  29. Recommended Sandy Pond Solution • Wachusett recommended as the preferred alternative based on: • Lowest cost • Wachusett PW = $32.2 M • Pratts Junction PW = $32.3 M • Quinsigamond Junction PW = $36.1 M (all estimates are study grade – ±25%) • Better system performance compared to Pratts Junction option • Less permitting risk than Pratts Junction option (W-23 conversion) or Quinsigamond Junction (new substation)

  30. Wachusett Construction Issues • Construction Grade estimate developed for the preferred alternative • Identified wetland issues that limit use of existing Wachusett site • Requires construction of Gas Insulated Substation

  31. Wachusett GIS Layout

  32. Revised Wachusett Cost • GIS design increases cost of Wachusett substation by $5 M (+19%) • Revised Comparison of Project Costs • Wachusett (Air): PW = $32.2 M • Pratts Junction: PW = $32.3 M • Quinsigamond Junction: PW = $36.1 M • Wachusett (GIS): PW = $37.2 M

  33. Assessment of Alternatives • Wachusett Alternative • PW = $37.2 M • NEP land at existing substation • Balanced system flows • Supports Millbury/Northboro Rd voltage

  34. Assessment of Alternatives • Quinsigamond Junction Alternative • PW = $36.1 M • Requires purchase of land • Higher permitting risk • Balanced system flows • Supports Millbury/Northboro Rd voltage • Transient Stability analysis and detailed site engineering may identify additional costs

  35. Assessment of Alternatives • Pratts Junction Alternative • PW = $32.3 M • NEP land at existing substation • Requires conversion of N-40/W-23 circuit from 69 kV to 115 kV • Higher permitting risk • Requires construction of a new 345-115 kV substation near Millbury if line cannot be permitted • Unbalanced system flows • Eight (8) 115-69 kV transformers at Pratts Junction • Heavy reliance on converted N-40/W-23 circuit to Northboro Road • Support for Millbury/Northboro Rd voltage • Transient Stability analysis and detailed site engineering may identify additional costs

  36. Recommendation • The Wachusett location is still the recommended option • Technically superior and less permitting risk than Pratts Junction option • Similar cost and less permitting risk than Quinsigamond Junction option • Changing recommendation will delay installation by at least one year • Additional engineering minimizes uncertainty with the Wachusett option compared to Pratts Junction or Quinsigamond Junction

More Related