1 / 21

Undulator Assembly and Installation Planning

Undulator Assembly and Installation Planning. Rodd Pope, SLAC. By Scott Doran, ANL. UNDULATOR CELL ASSEMBLY NEXT CELL UNDULATOR SHOWN FOR CLARITY. By Scott Doran, ANL. UNDULATOR CELL ASSEMBLY NEXT CELL UNDULATOR SHOWN FOR CLARITY. Collaboration Roles and Responsibilities (abridged).

vasquezs
Download Presentation

Undulator Assembly and Installation Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Undulator Assembly and Installation Planning Rodd Pope, SLAC

  2. By Scott Doran, ANL UNDULATOR CELL ASSEMBLY NEXT CELL UNDULATOR SHOWN FOR CLARITY

  3. By Scott Doran, ANL UNDULATOR CELL ASSEMBLY NEXT CELL UNDULATOR SHOWN FOR CLARITY

  4. Collaboration Roles and Responsibilities(abridged) • ANL – Stephen Milton Geoff Pile • Design the System and Sub-assemblies minus WPM/HLS • Supply Designed Sub-assemblies • Provide Expertise • SLAC Metrology – Robert Ruland • Design and Supply WPM/HLS System • Undulator Tuning & Quadrupole Measurement • Develop and Test Fiducialization Procedures • Provide Expertise • SLAC Assembly & Installation – Ben Poling • Girder Assembly • System Installation • Material Handling and Storage • Provide Expertise

  5. Assembly, Installation, and Maintenance Group • Undulator Assembly, Installation and Maintenance Group (U-AIM) • Supervisor – Ben Poling • Principal Technician – Ed Akerstrom • Principal Technician – Nick Horton • Material Handling, Assembly Preparation, Installation Planning • Three Engineering Assistants • Michelle Chan, William Rowan, Austin Schuh • Summer Support of Design, Engineering, Production Activities

  6. Assembly – Installation Outline • Receive Assemblies, Sub-assemblies, and Kits • Inspect, Modify, Store • Girder Rough Assembly • Girder Precision Assembly • Anchor Installation (Davis-Bacon) • Pedestal Installation (Davis-Bacon) • Girder Installation (Davis-Bacon) and Mover Startup • Vacuum System Completion • WPM/HLS Installation and Startup • Undulator Magnet Installation

  7. Assembly, Install, & Storage Space Undulator Tunnel B081 – MMF Tuning/Fiducialization B750 – Storage/Assembly

  8. Undulator System Girder Assembly Precise/Vacuum Assembly performed in a control environment Field Installation

  9. SLAC Magnetic Measurement FacilityWolf, Zachary, LCLS Management Presentation, April 11, 2006, Slide 3 • Floor plan divided into three functional areas • Magnetic Measurements (± 0.1º C) • Fiducialization and Assembly (± 1º C) • Storage (± 2.5º C) Assembly Area Storage and Queuing LCLS-TN-04-1

  10. Schedule, Summary

  11. Component Delivery Schedule – 7/10/07 Actual Plan

  12. Component Deliveries by 1/10/2007(+6 Months from Now)

  13. Next Six Months • WPM and HLS Hardware Delivered • Undulators RFI • Component Deliveries Minus RF BPMs and Vacuum Chambers • Cable Plant • Design Review Complete • Procurements Placed for Materials and Labor • Early Occupancy of Undulator Hall • Pedestal Installation Contract Let • Girder Installation Contract Out for Bid

  14. End of Presentation

  15. Component Delivery Schedule – 2/10/07

  16. By Scott Doran, ANL SHORT BREAK

  17. By Scott Doran, ANL SHORT BREAK CROSS SECTIONS

  18. By Scott Doran, ANL LONG BREAK

  19. By Scott Doran, ANL LONG BREAK CROSS SECTIONS

  20. Component Delivery Schedule

  21. Girder Assembly Flow ANL Supplied ANL Supplied

More Related