Project Management – Critical Path Analysis

DESCRIPTION

Project Management – Critical Path Analysis. Learning Objectives. Be able to identify and order tasks and sub-tasks. Be able to apply Critical Path Analysis to a complex networked project. Project Management – Critical Path Analysis. Characteristics of Projects. Large.

1 / 8

Download Presentation

Project Management – Critical Path Analysis

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management – Critical Path Analysis Learning Objectives • Be able to identify and order tasks and sub-tasks • Be able to apply Critical Path Analysis to a complex networked project

  2. Project Management – Critical Path Analysis Characteristics of Projects Large • Lots of people involved • Lots of tasks involved • Can go on for many years Complex • “One-offs” or infrequent activities • High degree of dependency between tasks

  3. Project Management – Critical Path Analysis Network Analysis • Developed to reveal dependencies/independencies • Uses standard symbols to flowchart project Activity Dummy activity Event number 3 Latest finish time for Any activity entering 30 20 Earliest start time For any activity leaving Event

  4. Project Management – Critical Path Analysis Activity 1 – Making a cup of tea (team of 7) • Create a Critical Path analysis for making a cup of tea • The tea must be made in no more than 60 seconds • Assume a team of 7 so tasks can be done in parallel

  5. Project Management – Critical Path Analysis Activity 1 – Making a cup of tea (team of 7) 12 Get milk from fridge 55 5 Add milk Plug kettle in Boil kettle 0 1 2 3 Put water in kettle 10 13 43 0 10 13 43 0 Pour water in cup Take cup from cupboard 10 11 13 Take spoon from drawer 4 Remove Tea bag 48 55 60 48 55 60 40 4 7 Sugar on spoon 9 8 37 4 Take sugar from cupboard Sugar In cup 43 10 40 7 6 Take tea from cupboard 37 4 Tea in cup • Colour in the critical path 5 40 4

  6. Project Management – Critical Path Analysis Activity 1 – Making a cup of tea (alone) • What would change? • Would the critical path change?

  7. Project Management – Critical Path Analysis Activity 2 – Holly Bush House 2 Learning Outcomes • A critical path analysis for a multi task project

  8. Project Management – Scoping a Project Model Answer – Holly Bush House 2 10 16 45 12 74 Prepare documentation 48 4 7 39 13 19 45 Discuss With client Answer queries Prepare 2nd draft Discuss With client Submit plans Completion meeting 3 2 0 1 6 14 11 15 13 17 18 4 30 34 2 8 28 First draft 0 42 Client briefing 0 Survey 16 88 Lay foundations Install windows 62 74 20 Approval of plans 90 46 48 Build walls 116 120 94 120 94 Show neighbour Show neighbour 5 Order windows & doors 8 Request cheque 13 39 45 19 16 83 116 9 16 45