An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SMART METERTEXAS Status Update June 17, 2010

  2. AGENDA • Release 1 Smart Meter Texas Online Portal Update • SMT Solution Update • Registration Statistics • Help Desk Statistics • REP Smart Meter Texas FTPS and API Integration • Process • Status • Summer And Fall Releases • Upcoming Events Information • Open Floor Discussion and Additional Questions 2

  3. Smart Meter Texas Release 1 Update • Points of Reference: • Data Repository, FTPS, and APIs went Live on January 31, 2010 • ‘Go Live” launch of the Smart Meter Texas Online Portal on March 15, 2010. • AEP has now been integrated for over two weeks and live with LSE 15 minute interval data to Smart Meter Texas. • The personal service assisted registration process is still available for interested REPs. Contact Jenina Smith at Jenina.Smith@SolutionsCubeGroup.com to obtain a registration packet with all the registration details. Self service registration will be implemented this summer. • The Advanced Metering Implementation Team and the Smart Meter Texas team conducted work sessions in Austin and defined the scope and design of functionality for a summer 2010 release of Smart Meter Texas. The summer release is now finishing up on development for the last functions, completing vendor system testing and well into the first week of TDSP UAT testing. • The Advanced Metering Implementation Team and the Smart Meter Texas team are continuing work sessions in Austin to define the scope and design of functionality for a Fall 2010 release of Smart Meter Texas. These design work sessions are scheduled on the PUCT calendar and go through September 22 this year. 3

  4. Release 1 Smart Meter Texas Online Portal Update • Release 1 Statistics (after 94 days) • 1,207,950 AMS meters • Oncor – 917,333 • CenterPoint – 267,990 • AEP Central – 22,627 • AEP North - 0 • 4 TDSP entities created and registered successfully on SMT portal • 69 TDSP users created • 2448 residential users have created accounts • 28 REP entities created and registered successfully on SMT portal • 325 REP users created • 24 NRC (Commercial) entities created • 113 HAN devices successfully provisioned 4

  5. Release 1 Smart Meter Texas Online Portal Update 5

  6. REP SMT FTPS and API Integration Process • One-on-one SMT Integration Process • Contact Jenina for insertion into process flow • Provide Jenina with requested information jenina.smith@solutionscubegroup.com • SMT FTPS integration process central point of contact that will work with you will be Bret Simon bret.c.simon@us.ibm.com • Will receive one-on-one assistance, emails, calls, Q and A and private FTPS integration session scheduling to meet your personal schedule • Please note that the goal set and agreed to by AMIT is to migrate all REPs from the individual TDSP FTP sites onto the Smart Meter Texas FTPS site by end of May. • Note due to the recent influx of interest by REPs to integrate to the SMT FTPS site that are not currently integrated. The date for removal of TDSP 15 minute interval data from the TDSP FTP sites has been temporarily extended . Please contact your TDSPs with needed extension time period. 6

  7. Current Status of REP Integration Process • 57 REP accounts successfully created in SMT production FTPS • 62 REPS successfully integrated into SMT testing FTPS • 69 REPS at some stage of FTPS integration process • TDSP FTP site to shut-down soon • API integration process • 3 REPS completely integrated with testing API environment • 3 REPS in process of testing API integration • 7 more REPS showing interest in API interface

  8. Summer and Fall Release FunctionalityRedistributed • On May 25th in the AMIT meeting in Austin it was agreed that the Summer and Fall release functionality will be redistributed • Redistribution was based on the following: • Design was complete and ready for summer • Or vice versa the design is more complex and still in process so it must wait for fall • Development can be completed in time for Summer release 8

  9. Fall Design Approach • Late July upon request one on one requirements design workshops with REPs to understand individual requirements to ensure that Fall baseline framework for HAN and third parties as well as other functionality will support future needs. • August – September AMIT Fall functionality requirements and design sessions. • August – September parallel AMIT HAN functionality design discussions as appropriate to support Fall third party and other functions. • Late July – September Market change request review, design, approval 9

  10. Summer Release Functionality • Implementation of self service registration for NRC (commercial) and REPs • Capability to view meter attributes and meter capabilities • Capability to view premise attributes • Ability to retrieve monthly billed usage data • Capability for customers to provisioning and de-provisioning HAN devices • Ability for customers to view HAN device details and device history • Provide automated reporting of Smart Meter Texas portal statistics i.e.. User counts, entity counts, HAN device counts, etc.. • Capability for re-branding Smart Meter Texas portal for REPs • Provide support for regulatory user and regulatory admin roles • Provide support for supplemental parties (i.e. friends or family members) 10

  11. Fall Release Functionality • Provide support for 3rd party user and 3rd party admin roles • Ability to request on-demand meter reads and poll for power status • Ability to subscribe and receive meter event notifications for outage and restoration. • Ability to subscribe and receive portal events • Change requests from the Market 11

  12. Up Coming Events • Bi-Weekly Smart Meter Texas Status Meetings on Thursdays • July 1, 2010 HAPPY 4th of July! • July 15, 2010 • July 29, 2010 • Continuing>>>>> • Through June REP Personal Service Registration to SMT Portal User Interface. Summer Release will Provide REP Self Service Registration. • Summer Release of Functionality for SMT by Mid August • Fall Release of Functionality for SMT 12

  13. Open Floor Discussion and Questions Open Forum 13