Overview of the Smart Meter Texas (SMT) Meter Reading Processing Timeline. Overview of the Meter Reading Processes. Consumer. SMART METER TEXAS Host. TDU. Meter Interval / Register Reads (LSE File Format). Meter Interval / Register Reads. MDMS VEE Processes. Meter Reading Timeline.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Overview of the Smart Meter Texas (SMT) Meter Reading Processing Timeline' - zyta


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

Overview of the meter reading processes
Overview of the Meter Reading Processes Processing Timeline

Consumer

SMART METER TEXAS

Host

TDU

Meter

Interval / Register Reads

(LSE File Format)

Meter

Interval / Register Reads

MDMS

VEE Processes

Meter Reading Timeline

Day 1

Day 1

Day 2

Day 2

HAN Device

(Real-Time Display)

RF Meter Reading Process

(Periodic Updates With Final Readings On Day 2)

MDMS

(Validate And Estimating Processes)

SMT

(FTP And DB Processes)


Overview of the smt processes
Overview of the SMT Processes Processing Timeline

Meter Reading Timeline

Day 1

Day 1

Day 2

Day 2

HAN Device

(Real-Time Display)

RF Meter Reading Process

(Periodic Updates With Final Readings On Day 2)

MDMS

(Validate And Estimating Processes)

SMT

(FTP And DB Processes)

SMT Processing Timeline

Day 2

Upon Receipt Of LSE Files, Files Are Placed In ROR Folder Within 30 Minutes

(Monitored On A 24 Hour Basis)

ROR Files

4 – 8 A.M.

Data Process #1

(0-5 Minutes)

12 – 2 P.M.

Data Process #1

(0-5 Minutes)

5 – 11 P.M.

Data Process #1

(0-5 Minutes)

Consumer

Meter

Readings

10:45 P.M.

Data Ld #7

(0-60 Min.)

1:45 A.M.

Data Ld #1

(0-60 Min.)

4:45 A.M.

Data Ld #2

(0-60 Min.)

7:45 A.M.

Data Ld #3

(0-60 Min.)

10:45 A.M.

Data Ld #4

(0-60 Min.)

1:45 P.M.

Data Ld #5

(0-60 Min)

4:45 P.M.

Data Ld #6

(0-60 Min.)

7:45 P.M.

Data Ld #7

(0-60 Min.)