1 / 17

Cleanness of the 3-4 cold beam lines

Cleanness of the 3-4 cold beam lines. C. Garion on behalf of TE/VSC with materials of Vincent Baglin. Outline: History: Status of 2009 cleaning Foreseen and additional activities on cold beam lines. Inspection and cleaning activities in sector 3-4 during LS1 Activity sequence Procedure

shasta
Download Presentation

Cleanness of the 3-4 cold beam lines

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cleanness of the 3-4 cold beam lines C. Garion on behalf of TE/VSC with materials of Vincent Baglin C. Garion Outline: • History: Status of 2009 cleaning • Foreseen and additional activities on cold beam lines. • Inspection and cleaning activities in sector 3-4 during LS1 • Activity sequence • Procedure • Schedule • Conclusion

  2. History: Beam vacuum line cleanness in sector 3-4 after incident • Contamination types: • MLI • Soot • (Debris) LSS4 LSS3 Soot MLI Contamination distribution: C. Garion

  3. History: Cleaningmethodsafter 3-4 incident (1) • Foam plugs for the soot: • Use of two plugs for horizontal and vertical parts of the beamscreen • Use of alcohol-wetted and dry foam plugs • Up to 50 passages in each direction withwetfoam plug and up to 15 passages with dry plug Example of C19R3.V2 C. Garion

  4. History: Cleaningmethodsafter 3-4 incident (2) • Air flux for the MLI: • 1st step: automaticpumping/venting • A cycle : 20 s pumping, 18 s plateau, 2 second vent • The pressure is reduced from 1 atm to 0.8 atm in 2 s • (to be compared to the arc pump down of 200 mbar/h) • Apply this process for 30 min (40 pumping/venting cycles) • 2ndstep: aspiration with local pertubationcontrolled by endoscope • nozzleblowsfiltered air, the MLI residuesleftbehind the beamscreen and the RF fingers are directedtowards the beam aperture wherethey are aspiredaway. • Time : 5 min per PIM, speed of 3 m/min along the beamscreen C. Garion

  5. History: cleannessafter 3-4 incident • Acceptance criteria: • After discussion with AB-ABP and following Chamonix it was agreed with the management that : • 1 fibre per half-cell • 2 debris (MLI or other less than 1 mm2) per magnet • can be left in the beam tube after the cleaning process ! • Few pictures of non-conformities: A32L4 V1 Q34R3 V1 Q29L4 V1 C. Garion

  6. Foreseen activities on cold beam lines (at the LS1 start). 4 Magnet exchanges  Point 3 Point 4  Damaged bellows (PIM cutting to be confirmed at opening: not to be changed) «standard» endoscopy (54 m in one direction per line) C. Garion

  7. Foreseen and additional activities on cold beam lines. • 2 additional openings are asked for inspection and investigation (Endoscopy). • Extended endoscopies. • Air flux for MLI removal • New opening: • QBBI.A14R3 (V2); • QBBI.A20R3 (V2)  Point 3 Point 4  C. Garion

  8. Inspections and cleaning activities in sector 3-4 during LS1 (1) Sequence: Prudent endoscopy*  analysis Cleaning by pulsed air flow Endoscopy Cleaning by pulsed air flow  Point 3 Point 4  Cleaning by pulsed air flow (24h) toward point 4 Analysis and decision * Prudent endoscopy: if too many debris are observed, the endoscopy will be stopped and the cleaning carried out endoscopy. C. Garion

  9. Inspections and cleaning activities in sector 3-4 during LS1 (2) Sameprocedure as in 2009 willbeapplied (EDMS 989454) Samematerial, available C. Garion

  10. Schedule of inspection and cleaning activities in 3-4 • All interconnections and beam vacuum lines related to these activities in sector 3-4 are opened including the QBBI.A14R3 and QBBI.A20R3 • VSC activities in parallel with SIT reconnection work. No closure of the beam vacuum lines (PIM installation before the end of the activity) • Start of VSC activities beginning of August (8 August) • ~ 3 weeks in total • From point 4 first (to avoid interaction with optical fibre activity, t.b.c.); • Mid august from point 3 C. Garion

  11. Conclusion A scenario of inspection and cleaning of the cold vacuum beamlines in sector 3-4 isproposed. The additionalwork for the SMACC team has been minimizedwhileprovidinga maximum of informations and efficiency of the cleaning. A cleaning of the 2 beam vacuum lineswillbecarried out based on pulsed air flow. Procedure and tooling have already been applied in 2009. C. Garion

  12. Back up slides Cleannessafter incident PIM status Interconnectionstatus C. Garion

  13. UFO activity To beinspected, mostlikely a consequence of 3-4 incident Source probablyidentified - ongoing Inspected and no cause found Courtesy of T. Baer C. Garion

  14. Beam screens with soot in tunnel : B19R3 B19R3.V2 before cleanning After cleanning end entrance mid V. Baglin Chamonix 2009

  15. Beam screens with soot in tunnel : C19R3 C19R3.V2 before cleanning After cleanning end entrance mid V. Baglin Chamonix 2009

  16. RF ball test RF ball after test of V1 in sector 3-4: Few MLI chips found C. Garion

More Related