An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ADMINISTRACION DE LA PRODUCCION ADMINISTRACION DE PROYECTOS POR DR. C.P./ LIC. EDUARDO BARG

  2. ADMINISTRACION DE PROYECTOSCONCEPTOS PROYECTO: Serie de actividades relacionadas entre sí, que están dirigidas hacia un resultado común y cuyo desempeño requiere un periodo significativo. ADMINISTRACION DE PROYECTOS: Es la planeación, dirección y control de recursos ( personas, equipos, materiales) para cumplir con las restricciones técnicas (PARAMETROS) (ESPECIFICACIONES DE CALIDAD), de costo (PRESUPUESTO) y de tiempo (PLAN) de un proyecto. POR DR. C.P./ LIC. EDUARDO BARG

  3. ADMINISTRACION DE PROYECTOSCARACTERISTICAS • RELEVANTES E IMPORTANTES • DURACION LIMITADA • REQUIEREN RECURSOS PARCIALES DE LA ORGANIZACIÓN • OCURREN EN UN MOMENTO DETERMINADO PARA MEJORAR, AMPLIAR O REALIZAR UN NUEVO NEGOCIO • SURJEN DE PROBLEMAS U OPORTUNIDADES • EXISTE UN “ADMINISTRADOR DEL PROYECTO”. COORDINA AL PERSONAL PARA SATISFACER AL CLIENTE. POR DR. C.P./ LIC. EDUARDO BARG

  4. ELEMENTOS DE ADMINISTRACION DE PROYECTOS • GERENTE DE PROYECTO • EQUIPO DE PROYECTO • SISTEMA DE ADMINISTRACION DEL PROYECTO. • METODOS DE PLANIFICACION DEL PROYECTO • DIAGRAMAS VARIOS PARA LA ADMINISTRACION Y SEGUIMIENTO POR DR. C.P./ LIC. EDUARDO BARG

  5. ADMINISTRACION DE PROYECTOSESTRUCTURAS ORGANIZACIONALES POR DR. C.P./ LIC. EDUARDO BARG

  6. ESTRUCTURA DE LA DIVISION DEL TRABAJO • DECLARACION DE TRABAJO • TAREA • PAQUETE DE TRABAJO • PARAMETROS DE AVANCE DEL PROYECTO • ESTRUCTURA DE LA DIVISION DEL TRABAJO POR DR. C.P./ LIC. EDUARDO BARG

  7. ETAPAS EN LA ADMINISTRACION DE PROYECTOS ETAPA I DEFINICION ETAPAII PLANIFICACION ETAPAIII PUESTA EN MARCHA ETAPA IV CONCLUSION POR DR. C.P./ LIC. EDUARDO BARG

  8. ETAPA I :DEFINICION EVALUACION DEL PROYECTO POR DR. C.P./ LIC. EDUARDO BARG

  9. ETAPA II: PLANIFICACION DETERMINACION DE LA FRAGMENTACION DEL TRABAJO PLANIFICACION DE: CALIDAD TIEMPO DE EJECUCION COSTOS RECURSOS HUMANOS NECERSARIOS POR DR. C.P./ LIC. EDUARDO BARG

  10. ETAPA III: PUESTA EN MARCHA • RESOLVER • LAS • DIFERENCIAS • DEMANDAR • CEDER • PACTAR • CONTROL DE • DESARROLLO • ESTABLECER • EL ESTANDAR • 2. SUPERVISAR • LA EJECUCION • 3. TOMAR UNA • ACCION • CORRECTIVA • OFRECER • FEEDBACK • INTENCIONES • ACCIONES • RESULTADOS CONTRATAR MATERIALES, SUMINISTROS Y SERVICIOS NEGOCIOCION POR DR. C.P./ LIC. EDUARDO BARG

  11. ETAPA IV: CONCLUSION • ELABORACION DEL MANUAL DE OPERACIONES • CAPACITAR AL PERSONAL USUARIO • REASIGNACION DEL PERSONAL • DISPOSICION DE EQUIPOS, MATERIALES Y SUMINISTROS SOBRANTES • EVALUACION DE LA EXPERIENCIA • AUDITORIA FINAL • INFORME FINAL DEL PROYECTO • REVISION CON LA ALTA GERENCIA • DECLARAR EL PROYECTO TERMINADO Y EN PLENO FUNCIONAMIENTO POR DR. C.P./ LIC. EDUARDO BARG

  12. TECNICAS GRAFICAS PARA LA PLANIFICACION Y EL CONTROL DE PROYECTOS GANTT: GRAFICAS INDIVIDUALES Y DE AVANCE EN BARRAS C.P.M.: METODO DE RUTA CRITICA P.E.R.T.: TECNICA DE REVISION Y EVALUACION DE PROGRAMAS POR DR. C.P./ LIC. EDUARDO BARG

  13. P.E.R.T. PROGRAMA DE REVISION Y EVALUACION TECNICA • ES UN METODO DE PLANIFICACION DE RED FORMADO POR NODOS Y FLECHAS QUE CONSIDERA AL PROYECTO COMO UN CONJUNTO DEACTIVIDADES ENTRE LAS QUE EXISTEN RELACIONES DE PRECEDENCIA. POR DR. C.P./ LIC. EDUARDO BARG

  14. P.E.R.T. VENTAJAS • OBLIGA A ANALIZAR LAS TAREAS INVOLUCRADAS Y VER LAS PRECEDENCIAS DE TAREAS • PERMITE ESTIMAR EL TIEMPO DE TERMONACION Y EL COSTO TOTAL DEL PROYECTO • DETECTA TAREAS NO CRITICAS POSIBLES DE RETASAR • POSIBILITA ANALIZAR LAS CONSECUENCIAS DE CAMBIOS DE RECURSOS Y COMO AFECTAN LOS TIEMPOS Y COSTOS POR DR. C.P./ LIC. EDUARDO BARG

  15. P.E.R.T. CONCEPTOS PRELIMINARES • GRAPHE • ARCOS DIRIGIDOS • ARCOS NO DIRIGIDOS • BUCLE A • GRAPHE SIMETRICO A B • GRAPHR ANTISIMETRICO A B • CAMINO • CIRCUITO • LONGITUD DE UN CAMINO O CIRCUITO ( N° DE ARCOS) POR DR. C.P./ LIC. EDUARDO BARG

  16. P.E.R.T ELABORACION DEL DIAGRAMA DE RED • RED DE ACTIVIDADES EN NODOS (AON) ENFOQUE ORIENTADO A LAS ACTIVIDADES S T S Y U DEBERAN COMPLETARSE ANTES DE QUE SE INICIE T U POR DR. C.P./ LIC. EDUARDO BARG

  17. P.E.R.T ELABORACION DEL DIAGRAMA DE RED • RED DE ACTIVIDADES EN ARCOS (AOA) ACTIVIDADES = ARCOS NODOS = EVENTOS 1 S 3 4 U S Y T DEBERAN COMPLETARSE ANTES DE QUE SE INICIE U 2 T POR DR. C.P./ LIC. EDUARDO BARG

  18. P.E.R.T. OTROS CONCEPTOS • TIEMPO DE TAREA • TIEMPO DE INICIO/ TERMINACION MAS PROXIMO • TIEMPO DE INICIO/ TERMINACION MAS LEJANO • HOLGURA • RUTA • CAMINO CRITICO POR DR. C.P./ LIC. EDUARDO BARG

  19. P.E.R.T. TIPOLOGIA • P.E.R.T. NORMAL • P.E.R.T. ACELERADO • P.E.R.T. COSTO POR DR. C.P./ LIC. EDUARDO BARG

  20. PRINCIPIOS BASICOS DEL METODO P.E.R.T. • ESTABLECIMIENTO DE LAS PRELACIONES EXISTENTES ENTRE LAS DISTINTAS ACTIVIDADES. -- NOS INDICA EL ORDEN EN QUE DEBEN EJECUTARSE LAS ACTIVIDADES -- TIPOS DE PRELACIONES: TECNICAS, ECONOMICAS Y JURIDICAS -- SI UNA ACTIVIDAD A DEBE EJECUTARSE ANTES QUE B DIREMOS QUE A PRECEDE A B POR DR. C.P./ LIC. EDUARDO BARG

  21. CONSTRUCCION DEL GRAFO P.E.R.T ASIGNACION DE TIEMPO A LAS ACTIVIDADES • GENERALMENTE LA DURACION DE LAS ACTIVIDADES NO PUEDE SER FIJADA CON EXACTITUD DEPENDE DE CIRCUNSTANCIAS ALEATORIAS. • EL METODO P.E.R.T CONSIDERA TRES ESTIMACIONES DE TIEMPO DISTINTAS: • ESTIMACION OPTIMISTA (TIEMPO MINIMO SI TODO VA BIEN) • ESTIMACION MAS PROBABLE (TIEMPO NORMAL) • ESTIMACION PESIMISTA ( TIEMPO MAXIMO ANTE CIRCUNSTANCIAS TOTALMENTE DESFAVORABLES) POR DR. C.P./ LIC. EDUARDO BARG

  22. P.E.R.T OTRAS DEFINICIONES • HOLGURA: COMIENZO TEMPRANO – COMIENZO TARDIO O FIN TEMPRANO – FIN TARDIO - INDICA EL N° DE UNIDADES DE TIEMPO EN QUE PUEDE RETRASARSE LA REALIZACION DE LA ACTIVIDAD CON RESPECTO AL TIEMPO PERT PREVISTO SIN QUE LA DURACION DEL PROYECTO SUFRA NINGUN RETRASO. POR DR. C.P./ LIC. EDUARDO BARG

  23. P.E.R.T OTRAS DEFINICIONES • ACTIVIDAD CRITICA: AQUELLA CUYA HOLGURA TOTAL ES CERO • CAMINO CRITICO: AQUEL QUE VA DESDE EL VERTICE QUE REPRESENTA ELSUCESO INICIAL DEL PROYECTO AL VERTICE QUE REPRESENTA EL SUCESO FINAL, PASANDO SOLO POR LAS ACTIVIDADES CRITICAS POR DR. C.P./ LIC. EDUARDO BARG

  24. CONCLUSIONES • EL ÉXITO DE UN PROYECTO NO SE BASA SIMPLEMENTE EN ESTABLECER UN PROGRAMA PERT. NECESITA UN LIDER DE PROYECTO COMPROMETIDO, TRABAJO EN EQUIPO, Y UN CONTROL EFECTIVO. • REQUIERE DEFINIR CLARAMENTE RESPONSABILIDADES, UN SISTEMA DE REPORTE SENCILLO Y OPORTUNO, Y BUENAS PRACTICAS DE ADMINISTRACION, EN ESPECIAL DE RRHH. • POR LO GENERAL LOS PROYECTOS PUEDEN FRACASAR A PARTIR DE UNA MALA EJECUCION Y CONCEPCION DE LAS DOS PRIMERAS ETAPAS Y POR LA FALTA DE COMPROMISO DEL RESPONSABLE Y SU EQUIPO. • EL USO HABILIDOSO DE LOS METODOS PERT/CPM AYUDA A LOS GERENTES A: ORGANIZAR UN PROYECTO E IDENTIFICAR LA RELACION ENTRE SUS ACTIVIDADES, ELABORAR INFORMES DE PROGRESOS, ESTIMAR TIEMPO DE TERMINACION, PONER EN RELIEVE LAS ACTIVIDADES CRITICAS, IDENTIFICAR LAS ACTIVIDADES QUE TIENEN HOLGURA Y REASIGNAR RECURSOS EN FORMA PRODUCTIVA, ANALIZAR TRUEQUES ENTRE COSTO Y TIEMPO Y MEDIR DESVIOS TECNICOS, DEL PRESUPUESTO Y DEL PLAN. POR DR. C.P./ LIC. EDUARDO BARG