New York State Department of Transportation

New York State Department of Transportation. Superstructure (4) and Bridge (3) Replacements At Various Locations in Region 9 PIN 9806.82, Contract No. D900020 Broome, Tioga and Delaware Counties Draft Request for Proposals RFP Informational Meeting August 13, 2014.

rosie
Download Presentation

New York State Department of Transportation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New York State Department of Transportation Superstructure (4) and Bridge (3) Replacements At Various Locations in Region 9 PIN 9806.82, Contract No. D900020 Broome, Tioga and Delaware Counties Draft Request for Proposals RFP Informational Meeting August 13, 2014

  2. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020) Rules of Contact Peter Russell Attn: Superstructure and Bridge Replacements in R9 Design-Build Project Office of Contract Management New York State Department of Transportation 50 Wolf Road, 6th Floor Albany, New York 12232 Peter.Russell@dot.ny.gov

  3. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020) Agenda • Project Overview • Department’s Goals & Project Requirements • Scope of Work • Status of: ROW and Utilities • General Contract Information • Alternative Technical Concepts • Procurement Schedule • One-on-One Meetings • RFP Content • Quality Control & Quality Assurance • Evaluation and Selection • Additional Information and Submission Guidelines • Questions and Answers

  4. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)General Location 4

  5. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)General Location 5

  6. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)General Location 6

  7. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)General Location 7

  8. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)General Location 8

  9. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)General Location 9

  10. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Goals • Replace superstructure of four bridges in Region 9 (Base Project) • Replace three CBOW bridges in Region 9 (Option) • Ensure the safety of the traveling public • Ensure coordination with all utility owners, third parties, and the surrounding residential community • Ensure a long-service life for all Project elements to satisfy long term preservation goals • Ensure compliance with the Project’s environmental commitments

  11. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Goals (Continued) • Maximize the beneficial impact of the public investment in the Project by • Providing cost-effective solutions that maximize value over the lifespan of the Bridges; • Sequencing construction to minimize effects on vehicular traffic operations; • Reducing future maintenance requirements; • Minimizing effects on residential neighborhoods and business communities • Deliver Project Safely, On Schedule, On Budget, and Environmentally Compliant. • Provide best value to the Department

  12. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)General Scope of Work Base Project: • Superstructure replacement for four bridges in Broome and Tioga Counties • Removal of existing superstructure • Modifications of substructures as necessary to accommodate new superstructure Option: • Complete replacement of three bridges over Pea Brook and Pea Brook Tributary on NYS Route 97 in Delaware County (Option) • Removal of existing substructure and superstructure • Construction of new bridges, including new foundations • Development of single SWPPP for all replacements (if required) • Remediation and disposal of Asbestos Containing Materials (ACMs)

  13. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)General Scope of Work (Continued) Base Project and Option: • Reconstruction of approach roadways as necessary to connect to the new structures, including correction of superelevation rates • Development of WZTC Plan for each site • Coordination with and/or preservation of existing utilities • Design and installation of new guide railing / bridge railing. • Avoid existing environmental constraints • Threatened and endangered species • Farmlands • Wetlands

  14. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Right-of-Way • The Department owns all Right-of-Way for the existing structures. • No additional Right-of-Way acquisitions or temporary easements are anticipated to be required for this project. • Any Right-of-Way fencing damaged or removed by the Design-Builder during construction shall be replaced with new Right-of-Way fencing meeting current Department standards.

  15. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Utility Coordination – Existing Utilities In accordance with Part 4 – Utility Requirements, Design-Builder is responsible for: • Verifying utility facility locations; • Identifying & resolving any conflicts not yet documented; • Coordinating with utility owners for utility relocations; • Providing stakeout and final layout of utility relocations; • Protecting existing utilities; • Cost to repair damages to utilities caused by Design-Builder; • Informing the Department of all meetings/correspondence with utility owners.

  16. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Utility Coordination – Existing Utilities • Base Project : • Noutility impacts are anticipated in connection with any of the superstructure replacements contained in the Base Project • Option: • Verizon: • Verizon shall be responsible for any necessary relocations of their aerial facilities due to construction of wing walls of the new bridges • NYSEG: • NYSEG shall be responsible for any necessary relocations of their aerial facilities due to construction of wing walls of the new bridges

  17. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Contract Information • Lump Sum Design-Build Contract; • Best Value Selection Process (50% Price, 50% Quality); • Project Completion Date shall be the earlier of: • November 31, 2016; or • The number of days past NTP proposed by the successful Proposer on Form SCD (ITP Appendix E) • There is a Payment Schedule provided in the RFP; • Stipend to Unsuccessful Proposers (50% of Qualified Costs, $75K max.); Must satisfy criteria in ITP General Instructions; • Liquidated Damages will be imposed for not meeting the Project Completion date and for Impacts to Traffic in excess of the number of calendar days indicated on Form SCD; • Escrow Submission of Bid Documents for Successful Proposer.

  18. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Contract Information (Continued) • There is a Buy America Clause • There is an Iran Divestment Act Clause • There is a DBE Participation Goal of 11% • All ROW owned by NYSDOT • Any additional Environmental and Construction Related Permits by Design-Builder

  19. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)ATCs • Alternate Technical Concepts (ATCs) are proposals from the Proposer to design and construct the Project in a manner that is different than the RFP requirements, and which: • are submitted to the Department for review and consideration prior to Proposal submittal; • have significant savings in time, reduction of traffic impacts, community disruption, project costs, environmental impacts, and/or other beneficial impacts to Project parameters; • in the Department’s judgment offer an equal or superior Project.

  20. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)ATCs (Continued) • Proposers may submit, on a confidential basis, up to five (5) proposed alternatives to the RFP requirements for the Department’s pre-approval; • The proposed end product of each alternative must, in the Department’s judgment, be equal to or better than the Work product described in the RFP Documents; • The Design-Builder is solely responsible for obtaining approvals from any local municipality, public agency or permit issuing agency for ATC concepts which would affect their facilities, operations or issued permit • Form ATC to be submitted with each proposed ATC.

  21. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Anticipated Procurement Schedule

  22. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)One-On-One Meetings • If One-On-One Meetings are held, at least one meeting will be held with each Proposer; • One-On-One Meetings will be recorded; • Department reserves the right to disclose to all Proposers any issues raised during the meetings that may materially affect the Project; • Department will not disclose information pertaining to an individual Proposer’s technical concepts, proposal or ATCs; • Additional One-On-One Meetings may be held if required to review ATCs or if the Department believes it is warranted.

  23. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Request for Proposals (RFP) Documents • RFP Documents: • Instructions to Proposers • Part 1: D-B Agreement • Part 2: General Provisions, Section DB 100 and Appendices • Part 3: Project Requirements (Scope of Work) • Part 4: Utility Requirements • Part 5: Special Provisions • Part 6: RFP Plans • Part 7: Engineering Data • Part 8: Special Specifications (Including New DB Specifications) • Part 9: The Design-Builder’s Proposal • Part 10: RFP Addenda (If Any) • Reference Documents: On Department’s web site (Not Part of the Contract Documents)

  24. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020) Request for Proposals (RFP) Documents (Continued) • RFP Documents: • Instructions to Proposers • General Instructions • Appendix A – Project Information • Appendix B – Administrative Submittal Requirements • Appendix C – Technical Submittal Requirements (Three Volumes) • Appendix D1 – Price Proposal Submittal Requirements (Base Project) • Appendix D2 – Price Proposal Submittal Requirements (Base Project plus the Option) • Appendix E – Forms • Appendix F – Conflicts of Interest Policy • Appendix G – Abbreviations and Definitions

  25. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020) Request for Proposals (RFP) Documents (Continued) • Instructions to Proposers: • Appendix C • Volume 2 (Applicable to Base Project Plus the Option) • Section 1 – Key Personnel and Firm Experience • Section 2 – Management Approach • Section 4 – Project Support • Appendix 2A (Applicable to the Base Project) • Section 2 – Management Approach (cont.) • Section 3 – Technical Solutions Narratives • Attachment A – Technical Solutions (Drawings) • Attachment B – Technical Solutions (Project Schedules) • Appendix 2B – (Applicable to the Base Project plus the Option) • Sections same as Appendix 2A

  26. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Quality Control (QC) • QC is Design-Builder’s Responsibility • Design-Builder shall appoint a QC Manager responsible for QC Plan for both Design and Construction • Design QC shall be performed by the Designer in accordance with the QC Plan • Construction Inspection shall be performed by an Independent Engineering Firm (Hired by the Design-Builder) • Materials Testing shall be performed by an Independent Materials Testing Firm or Laboratory (Hired by the Design-Builder) • The Materials Testing Firm shall report to the Construction Inspection Firm • Offsite Plant Quality Control shall be performed by the Department

  27. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Quality Assurance (QA) • Design and Construction QA is the Department’s Responsibility • The Department may perform QA on any of the Design-Builder’s Design and Construction activities • The Department will utilize an independent Consultant to perform QA of the Design-Builder’s Designs • Construction QA will be performed by Department staff • Offsite Plant Quality Assurance will be performed by the Department

  28. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)RFP Evaluation and Selection Pass/Fail Evaluation Factors • Legal – Financial – Administrative – DBE Compliance - Price Proposal (Bond/Conformance) Quality Evaluation Factors (50%) • Key Personnel (25 points) • Management Approach (30 points) • Overall Design-Build Team Organization (8 points) • Design Management Plan (7 points) • Construction Management Plan (7 points) • Quality Control Plan (8 points) • Technical Solutions (35 points) • Design Approach (10 points) • Construction Approach (10 points) • Initial Baseline Schedule (15 points) • Project Support (5 points) • Proposal Format(5 points) Price (50%) Design-Builder must obtain a minimum score of 60 points on Quality Evaluation factors

  29. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Additional Information – Submission Guidelines • All proposals must be self-contained. • Proposals should not have links to external web sites. • Proposals should contain all information needed for evaluation. • Do not “assume the Department knows” your firm and it’s experience/qualifications.

  30. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Additional Information – Submission Guidelines • Submit ALL Forms required. • Do not alter any Form unless indicated on the Form. • Do not add any appendices or attachments to the Forms. • Do not include photographs or illustrations unless specifically indicated. • Do not submit • Form SA (Stipend Agreement) • Form BDEA (Bid Document Escrow Agreement) • PAB (Payment Bond (Labor and Material Bond)) • PEB (Performance Bond (Faithful Performance Bond))

  31. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Additional Information • Responses to Proposer Questions will be posted on the Department’s Project Web Site • Reference Documents are Posted on the Department’s Project Web Site: https://www.dot.ny.gov/main/business-center/designbuildproject8 • Reference Documents include: • Design Reports • Bridge Inspection Reports • Record Plans • Asbestos Assessment Reports • ACE Nationwide Permit • NYSDEC Section 401 Water Quality Certification • NYSDEC Timber Rattlesnake Fact Sheet

  32. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Rules of Contact Peter Russell Attn: Superstructure and Bridge Replacements in R9 Design-Build Project Office of Contract Management New York State Department of Transportation 50 Wolf Road, 6th Floor Albany, New York 12232 Peter.Russell@dot.ny.gov

  33. Superstructure and Bridge Replacements in Region 9Design-Build Project (PIN 9806.82; D900020)Questions and Answers Questions ?