1 / 13

Alternative Public Works Procedures Sunset Review :

Alternative Public Works Procedures Sunset Review :. Legislature Should Continue Authority to Use Alternative Procedures. Proposed Final Report. Mark Fleming, JLARC Staff. State Law Governs Public Works Construction in Washington. Public Bodies. Largest Construction Programs:.

olympe
Download Presentation

Alternative Public Works Procedures Sunset Review :

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Alternative Public Works Procedures Sunset Review: Legislature Should Continue Authority to Use Alternative Procedures Proposed Final Report Mark Fleming, JLARC Staff

  2. State Law Governs Public Works Construction in Washington Public Bodies Largest Construction Programs: State Agencies • Dept. of Enterprise Services Higher Ed Institutions • University of Washington • Washington State University Local Governments • City of Seattle • City of Tacoma Ports Current projects total $2.4 Billion School Districts Special Purpose Districts Alternative Public Works Sunset Review Report Page No. 3 & 10

  3. Traditional Delivery Procedure: Design-Bid-Build Separates design and construction, used for projects of any size Contractor hired Awarded to responsible bidder with lowest responsive bid Construction cost established Invitation to bid Architect/ Engineer hired Phases: Predesign Design Construction Source: JLARC analysis of public works contracting procedures. Alternative Public Works Sunset Review Report Page No. 3-4

  4. Perceived Risks of Traditional Delivery Perceived Risk Impact Construction bid price may exceed budget Construction delay while project is redesigned and rebid Lack of construction expertise during design Unforeseen conditions must be addressed during construction Potential adversarial relationship with contractor Disputes may arise among parties over responsibility for changes Alternative Public Works Sunset Review Report Page No. 11-12

  5. Three Alternative Procedures Attempt to Address Design-Bid-Build Risks Chapter 39.10 RCW Alternative Method Authorized For: General Contractor Construction Manager (GCCM) Typically for projects $10M and above but may be authorized for smaller projects Design-Build (DB) Job Order Contracting (JOC) $350,000 or less Alternative Public Works Sunset Review Report Page No. 3-4

  6. Alternative Procedures Differ from Traditional Delivery Example: GCCM procedure Contractor hired Based on qualifications Contractor hired Based on qualifications Maximum allowable construction cost negotiated Maximum allowable construction cost negotiated Architect/ Engineer hired Architect/ Engineer hired Phases: Phases: Predesign Design Construction Predesign Design Source: JLARC analysis of public works contracting procedures. Alternative Public Works Sunset Review Report Page No. 4-7

  7. JLARC Recommends Continuing Authority for Alternative Procedures • Provide options to manage construction risk • Project managers value alternative procedures • Widespread use throughout nation • Public bodies in Washington follow statutory requirements to ensure public interest • Answers to sunset questions support continuation Alternative Public Works Sunset Review

  8. Public Bodies in Washington Follow Statutory Requirements to Meet Public Interest  Project Selection  Public Notice  Contract Limits • Detail to verify compliance with subcontract and contract limits is not always evident • GCCM subcontract limits • Job order contract limits Alternative Public Works Sunset Review Established statutory requirements governing: Report Page No. 13-17

  9. Capital Project Advisory Review Board Role is to Advise and Recommend CPARB performs role in several ways: • Makes recommendations to Legislature on public works and contracting issues • Organizes task forces and subcommittees to address contracting and public works issues • Seeks stakeholder input on alternative procedures • Collects quantitative and qualitative data for analysis • Initiated effort in 2008 to collect data on all public works projects over $5 million across the state Alternative Public Works Sunset Review Report Page No. 21-22

  10. CPARB Needs to Rethink Approach to Collecting Project Information • Project data is not likely to lend itself to meaningful comparisons • CPARB contributes most value as forum for discussion and developing consensus on policy and legislation • CPARB experience with task forces and subcommittees offers opportunity for timely policy input on issues related to public works construction Alternative Public Works Sunset Review Report Page No. 22-23

  11. Recommendations & Responses 1 The Legislature should reauthorize the alternative public works procedures, Chapter 39.10 RCW Agencies Concur: Agencies Concur: CPARB CPARB DES DES OFM OFM CPARB should 2 revise job order contract reporting to clearly identify separate contracts with and payments to the same contractor during the July 1-June 30 reporting period Alternative Public Works Sunset Review Report Page No. 25-26

  12. Recommendations & Responses (cont.) 3 Public bodies using GCCM should obtaininformation on project subcontract awards and payments and provide a final project report on their GCCM subcontracting to CPARB Agencies Concur: Agencies Concur: CPARB CPARB DES DES OFM OFM CPARB should 4 refocus its efforts and limited resources on collecting information that will more readily assist the Board in developing recommendations to improve public works delivery methods Alternative Public Works Sunset Review Report Page No. 31-35

  13. Contact Information Mark Fleming, Project Lead mark.fleming@leg.wa.gov 360-786-5181 Valerie Whitener, Project Supervisor valerie.whitener@leg.wa.gov 360-786-5191 www.jlarc.leg.wa.gov

More Related