LBT Q4 2007 Engineering Review AGW – Acquisition, Guiding and Wavefront Sensing Units
Highlights (Q4/2007) • Installed AGw #3 on telescope • Communication with GCS established LBT Q4 2007 Engineering Review
Open Issues • Technical • None • Schedule • Unit #2 delayed • Financial • None • Resource • Need one more unit for Direct Gregorian Commissioning LBT Q4 2007 Engineering Review
Progress (Q4/2007) • AGw #3 Installation on telescope (Oct) √ • Acceptance test AGw #2 (Nov/Dec) (Jan 2008) LBT Q4 2007 Engineering Review
Planning (Q1/2008) • AGw #2 acceptance test (Jan) • AGw #2 delivery to Arcetri (Feb) LBT Q4 2007 Engineering Review