LBT Q4 2008 Engineering Review. HPOP Hardpoints Study and Rework. Highlights (Q4/2008). Conceptual design of Super Hardpoint completed Actively collaborating with the LSST engineering group designing the super-hardpoints. Progress (Q4/2008).
E N D
LBT Q4 2008 Engineering Review HPOP Hardpoints Study and Rework
Highlights (Q4/2008) • Conceptual design of Super Hardpoint completed • Actively collaborating with the LSST engineering group designing the super-hardpoints. LBT Q4 2008 Engineering Review
Progress (Q4/2008) • LSST engineers are doing the design work, we are meeting at least weekly to provide oversight and guidance. LBT Q4 2008 Engineering Review
Open Issues • Technical • Consistency in testing • Glass safety qualified • Schedule • 1st article end Q1, test & characterize in winter, full production in spring, install next shutdown • Financial • Funding committed • Resource • 1 People LBT Q4 2008 Engineering Review
Planning (Q4/2008) • Complete detailed design • Begin parts manufacture of a first article by the end of January. LBT Q4 2008 Engineering Review