50 likes | 176 Views
The LBT Q4 2008 Engineering Review highlights the completion of all necessary documentation, including O&M manuals, as-built drawings, and acceptance test documentation, finalized by December 22, 2008. All outstanding issues in technical, schedule, financial, and resource aspects were resolved, marking this quarter's progress as significant. Key accomplishments included completing the Acceptance Test Matrix and minor edits to documentation. Future planning for Q1 2009 is set, with project completion pending any requests for clarification or modifications.
E N D
Highlights (Q4/2008) • Completed all remaining documentation on Dec 22, 2008. • Includes O&M manual, as-built drawings and design, control strategy, and acceptance test documentation. LBT Q4 2008 Engineering Review
Open Issues • Technical • None • Schedule • None • Financial • None • Resource • None LBT Q4 2008 Engineering Review
Progress (Q4/2008) • Complete remaining documentation (Planned Nov 08) (Completed Dec 08) • Finish filling out Acceptance Test Matrix and Plan with final test results. (Completed) • Make minor edits to design documentation, O&M manual and control strategy. (Completed) • Finish edits to as-built drawings. (This is the primary speed bump due to overbooked drafting resources.) (Completed) LBT Q4 2008 Engineering Review
Planning (Q1/2009) • Project complete pending any requests for clarification or modification of the documentation. LBT Q4 2008 Engineering Review