Presented By: RealTimeSites wind.enavajo.org June 16 – 17, 2009. STEP #1: Allocating the Funds. NNDCD enters the allocation for the Chapters into the Budget Application. STEP #2: Chapter Budget Process. At this time, the status of all budgets will be “Pending”. STEP #3: Completing Budgets.
E N D
Presented By: RealTimeSiteswind.enavajo.orgJune 16 – 17, 2009
STEP #1:Allocating the Funds • NNDCD enters the allocation for the Chapters into the Budget Application
STEP #2:Chapter Budget Process • At this time, the status of all budgets will be “Pending”.
STEP #3:Completing Budgets • Chapters will fill out their budgets by completing the following: • Distributing their allocation • Filling out the 3 steps of the Budget Details: • Entity Details with emphasis on Plan of Operation and Justification • Program Performance (Form 2) • Personnel Changes if needed
STEP #4:Submitting the Budget Once their budget is completed, the Chapters will submit their budget for review and approval to LGSC. At this point, the status of the budget will change to “lgsc”.
STEP #5:LGSC Review LGSC reviews the budgets and will either approve or reject the Chapter’s budget.
STEP #5:LGSC Rejecting the Budget If corrections need to be made to the budget, LGSC will reject the budget. • The budget will be sent back to the Chapter for modifications to be made. • LGSC will include comments on what needs to be fixed upon rejection. • Once corrections are made, the Chapter will re-submit their budget for LGSC review.
STEP #5:LGSC Approving the Budget • Once LGSC approves the budget, the budget process is complete. • The status of the budget will now be “Approved”.