  1. Original PAR, Inc.

  2. Original PAR, Inc.: Sensitivity Analysis

  3. PAR, Inc.: Change profit contribution for standard bag to (1) $13; (2) $14

  4. Original PAR, Inc.

  5. PAR, Inc.: Change RHS of Finishing constraint to (1) 899 hours; (2) 909 hours

  6. Shadow Price of Finishing Time:$6.9375 Finishing Time is the most valuable resource (original problem) because its shadow price is the highest Change RHS from 709 to 899 (obtain an additional 190 hours), will increase profit by $6.9375 for each additional hour within the allowable range 190 x $6.9375 + $7674.9375 = $8993.0625 (new objective function value)