1 / 15

SE Joint Firelink and FiReControl Project

SE Joint Firelink and FiReControl Project. CFO Martin Burrell FiReControl and Firelink Project Director. Objectives. General update on the Firelink and FiReControl projects Introduce the papers submitted separately Advise of forthcoming regional decisions. Firelink.

lorin
Download Presentation

SE Joint Firelink and FiReControl Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SE Joint Firelink and FiReControl Project

  2. CFO Martin Burrell FiReControl and Firelink Project Director

  3. Objectives • General update on the Firelink and FiReControl projects • Introduce the papers submitted separately • Advise of forthcoming regional decisions

  4. Firelink • Airwave – Macquarie ( New owners ) implement change of Airwave management team. • Firelink schedule • Confusion over call off items functionality and use for Regional control (Pump Bay Voice Terminals). May delay Statement Of Brigade Requirements. (SOBR) • Take up of early Mobile Data Terminals may affect schedule as these are due to be fitted at Phase B of Firelink • IDDS – will now be Quality Audited by Mason Communications. A marked improvement is expected. Currently no SE IDDS signed off.

  5. Firelink • Costs • Multimillion pound budget for interim solution. Taskforce meetings in FRS’s starting 1st October. • PBVT costs could double to meet FiReControl requirements. (Request To Talk function must be added) • On going concerns over cost of call off contract

  6. FiReControl

  7. Accommodation

  8. Accommodation • Practical completion/lease due 14th May 07 • Early occupation an option, but other considerations (business rates, H&S) • Facilities management & other decisions needed from the region if the LACC is not making decisions by early December 2007. • Facilities Management (by early December); • Utilities, early occupation; etc (April/May 08) • High quality building • Security checks on all staff and Board Members – 3 month process

  9. Business Case • There is to be a review of Assumptions – led by Finance Working Group • Bottom Line more important than principles and discussion • Current operating costs being requested through Finance Working Group • Needs to take account of costs of “out-of-scope” and “in-scope, in-FRS”, I.e. costs that will remain with FRS after cutover • Benefits management – ongoing cost reporting (again through FFWG)

  10. Implementation Funding • New burdens process gradually being understood – not a bid or a claims process, but CLG submits estimates • Some finance has been confirmed in Circulars • Some held back “depending on Checkpoint 1 and Resource Plan” • May shortly have to do rapid response on 3-year budget needs • Grant structure all altered – future funding may be RSG (resisted by FFWG as not flowing), or ring-fenced, or passed to Region to disburse to FRSs

  11. Transition Planning • Transition plans being developed; • Transition Governance letter from Peter Betts requesting CFOs to sign off prioritisation of FiReControl and readiness of internal FRS project structures • Checkpoints and Gates to be signed off by CFO/PO. Some information still awaited from EADS and CLG • Some S31 funding now, more depending on progress • Major risks: data/IT systems; Convergence (information from EADS/CLG delayed) • EADS: • Not where they would wish to be, but confident in achieving Oct 09 cutover

  12. General • LACC • Shadow company incorporated 14th Aug 2007. Registered Number 632450 • First board meeting to be set up – 1st week November? • Insurance • SLAs • HR policies being drafted for decision by LACC early 2008 • Shift patterns • Staffing numbers • Staff selection measures • Terms and conditions

  13. Decisions required by Regional Management Board • South East Fire and Rescue Company LTD • Formulation of LACC • Agree Members’ Agreement, Memorandum and Articles of Assoc. • Cost Apportionment

  14. Decisions required by Regional Management Board • HR • TUPE - FRSs or LACC to make redundancies? • RCCD recruitment – Panel interview RMB representation 19.11.07 • Financial and Legal Support • Recruit Regional Treasurer + buy in specialist advice as and when required via Diane Henshaw

  15. Questions?

More Related