EMC Status Report: November 2003 Roger Barlow. Events since last report (25 th Sept.) The ROD Current status Electronics Neutron Generator Light Pulser Chillers Data Quality -Trickle Injection Christmas plans Running in 2004. ADB happenings.
E N D
EMC Status Report: November 2003Roger Barlow • Events since last report (25th Sept.) • The ROD • Current status • Electronics • Neutron Generator • Light Pulser • Chillers • Data Quality -Trickle Injection • Christmas plans • Running in 2004
ADB happenings • 4 dead ADBs (Sept 25) became 6 (+1 noisy CARE) 3 in FB, 1 in BB, 2 in EC • The ROD • Forward Barrel : Fixed 3 ADBs. • Endcap: correct pipe in East, assess in West • Wahid moved way up the learning curve • Attempt to fix Endcap East by IOB replacement. Fail (and lose neighbour) Score -1 • backward barrel left alone (door). Spontaneous cure. Score +1 • Replaced FB ADB became noisy Now have 4 dead/noisy ADBs
Readout status Data from latest Light Pulser calibration run
Current Status: Electronics Dan’s next trip being organised for Jan/Feb 2004
ROB: Install Neutron Generator • It’s here. It works. It’s paid for. • Source calibration takes 30’ • Go back to 105 day between calibrations • Use `naturally occurring’ down times • Detailed instructions for shift crew to page Source Shifter • Small work needed • Flashing blue light for operation during access • LV power supply surge protect and remote on/off control
Current Status: Light Pulser • Used without airconditioning in cabinets (instability) • Used for detecting dead readout in global detector calibration and independently by EMC • New units on order, here December for installation over shutdown
Current Status: Worries(1) Endcap chiller. Not working (pump was dead, heating element for bypass line has problems + leaky valve…) and not understood. Leaking freon. Backup being used.
Current Status: Worries(2) Re-engineering fan units in LV PS crates is going forward slowly/not at all. Currently 3 out of 12 crates done. There are no spare crates. If When one dies a replacement will have to be put together on the spot from spare parts.
Current Status: Data Quality • Run 4 looks OK. • Trickle injection indications are that low background data with reasonable inhibit window are fine
Mass plots Run 42118 – normal Run 42149 – trickle
Christmas plans Replace noisy barrel ADB with a ‘favourite’ Replace/reconnect Endcap East IOB Look at Backward Barrel miracle cure, replace a couple of ADBs with intermittent noisy CARE chips. Don’t go for Endcap West. Pipe problems. Will need time and thought and expertise. Not worth risk of breaking something… Take time. Use trusted components.
Outlook for 2004 • Anticipate starting with 1 dead ADB, to be fixed when we have plenty of time to work. • Anticipate/hope for reasonably low failure rate so need for RODs is reasonably low: 3-4/year.