Space Planning and Construction

Space Planning and Construction. RECENTLY COMPLETED PROJECTS. LDR Room Renovations Completed on August 21, 2013 Microbiology Lab Reorganization Completed on October 9, 2013 45 Willard Conference Room rehab Completed on August 13, 2013 50 Holden conversion of Video Vault Room

keilah
Download Presentation

Space Planning and Construction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Space Planning and Construction

  2. RECENTLY COMPLETED PROJECTS LDR Room Renovations Completed on August 21, 2013 Microbiology Lab Reorganization Completed on October 9, 2013 45 Willard Conference Room rehab Completed on August 13, 2013 50 Holden conversion of Video Vault Room Completed on August 16, 2013

  3. Microbiology Temp Lab at Aud C

  4. Completed Microbiology

  5. Completed Microbiology

  6. IN PROGRESS ED Triage – Framing, drywall and utilities in progress Infusion Center One Blackstone – underground plumbing complete, framing in progress

  7. ED / Triage July Update

  8. ED / Triage October

  9. ED / Triage October

  10. ED / Triage October

  11. Infusion

  12. Infusion

  13. Infusion

  14. PROJECTS ABOUT TO START Day Hospital / Behavioral Health – awarded, permit received, sccheduling materials and start date Lab Long Term Plan Phase 1 – Phlebotomy – bids received and in for evaluation

  15. PROJECTSIN PLANNING UroGyn Long Term Plan Sim Center Relocation to Zero Level Auds DaVinci Robot Operating Rooms Philanthropy Office Reorganization / Fit test Nursing Support Staff Reorganization / Fit test

  16. Partner Projects DOH Review – New Primary Care Center at Butler DOH Review – WIH Infusion Center at Kent Design and Construction Documents – Isolator Hood Project Design – New USP 797 Chemo Mixing Room Design – Tenant Fit Out of 1st floor new MOB building

  17. Partner Projects Study – New Hyperbaric Chamber Plan Review and Bid Documents – Medical Gas Upgrade Project OTHER PROJECTS Retail Pharmacy Study DOH Review – 5750 Post Road, East Greenwich Space Plan – 171 Service Road