An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilities, Planning, and Construction April 14, 2014 Construction Report

  2. Area Currently Under Construction/ Planning Facilities under Construction: V.R. Eaton High School 540,000 SF __________ Total 540,000 SF Facilities in Planning/Bidding Stage: Peterson E.S. Addition 14,000 SF Beck E.S. Addition 8,000 SF NHS Chiller Replacement NA Prairie View Drainage Improvement NA ____________ Total 22,000 SF Total Projects under Construction, Planning and Bidding: 562,000 SF

  3. V. R. Eaton High School Architect: Corgan Associates Contractor: Pogue Construction Company Const. Start Date: Spring 2013 Completion Date: August 2015 Status: • Pier drilling is complete • Geothermal wells are complete • Grade beams are 95% complete • Foundation slab is 50% complete • Rough electrical and plumbing is being installed • Site grading and utility installation is underway • Steel erection is approximately 10% complete (Please note that the aerial photo was taken in March and does not reflect April progress)

  4. May 2013 March 2014

  5. Peterson Elementary School Addition Architect: SHW Architects Contractor: Northstar Builders Const. Start Date: Spring 2014 Completion Date: August 2014 Status: • Classroom concrete slabs have been poured • Steel has begun to be erected for classrooms • Grade beams have been poured for stage/cafeteria/gym expansion

  6. January 2014 April 2014

  7. Beck Elementary School Addition Architect: SHW Architects Contractor: Balfour Beatty Construction Const. Start Date: Spring 2014 Completion Date: August 2014 Status: • Pier drilling is underway • Site work is underway

  8. Possible ONCOR Electric Power Distribution Line

  9. Miscellaneous Maintenance Projects • Prairie View Elementary School Drainage Improvement • Water drains toward the front of the building during heavy rains and flows into the building • Project will be to route water to a retention pond and ditch adjacent to FM 3433 • Possible replacement of the front driveway • Northwest High School • Replace a 22 year old chiller • Anticipating a major failure within the next year • Current chiller contains obsolete R-22 refrigerant • The repair cost does not justify the repair • The efficiency of the replacement chiller will provide reduction in energy cost

  10. Pending Project Close-Out Change Orders • Cox Elementary School • Love Elementary School • Subvarsity Stadium