NGAO System Design Phase Management Report - Replan. NGAO Meeting #6 Peter Wizinowich April 25, 2007. Presentation Sequence. Review of SEMP Status Review of Replan Budget Next Steps. SEMP Status. SEMP Tracking.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'NGAO System Design Phase Management Report - Replan' - jovita


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
ngao system design phase management report replan

NGAO System Design PhaseManagement Report - Replan

NGAO Meeting #6

Peter Wizinowich

April 25, 2007

presentation sequence
Presentation Sequence
  • Review of SEMP Status
  • Review of Replan
  • Budget
  • Next Steps
semp tracking
SEMP Tracking
  • Tracked (Excel) version of the plan posted at http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/SystemDesignPhasePlanning/NGAO_SD_schedule_v20_tracked_final.xls
  • Excel version highlights what’s complete, what’s late, what’s due within next month & status of work scope planning sheets.
semp summary 1
SEMP Summary 1
  • WBS 1. SD Phase Management
    • On-schedule, except for replan (~ 1 month late)
  • WBS 2.1. Science Requirements
    • 1 work scope planning sheet approved. No others submitted.
    • All 13 science cases scheduled for completion by end of April. None completed.
    • Version 1 of Science Case Requirements complete. Version 2 due in Mar/07
  • WBS 2.2-2.3. System Requirements Document
    • 1 planning sheet approved, 2 late.
    • Version 1 complete. Version 2 due in March. Need more feedback, especially on science operations requirements.
    • Version 1&2 of traceability matrix late.
semp summary 2
SEMP Summary 2
  • WBS 3.1.1. Performance Budgets
    • 8 planning sheets approved, 1 submitted, 5 late.
    • Model assumptions. 3 complete & 1 on schedule.
    • Model/tool validation. 3 complete & 2 late.
    • Performance budgets. 1 complete, 6 late (2 others due later).
    • Version 1 of summary late.
  • WBS 3.1.2. Trade Studies (29 total)
    • 12 planning sheets approved, 1 needs changes, 11 late.
    • 9 complete, 1 cancelled & 15 late.
  • WBS 3.1.3. System Architecture.
    • Version 1 should have started, but hasn’t.
  • WBS 3.4. Science Operations
    • 2 WBS elements should have been started pre-March, but haven’t & another 5 should have started in Mar.
  • WBS 3.5 Science Instruments
    • Only Interferometer started. 4 others should have been started & 1 is late.
  • WBS 4 SEMP
    • No significant work planned yet
meeting tracking
Meeting Tracking
  • The tracked version of the action items from each meeting are posted near the top of the meeting page
    • Meeting 2 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/061114_CIT_NGAO_Meeting_2
    • Meeting 3 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/061213_Remote_NGAO_Meeting_3
    • Meeting 4 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/070122_NGAO_Meeting_4
    • Meeting 5 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/070307_Remote_NGAO_Meeting_5
    • The bulk of the action items are incomplete
    • Remember to look at these action items for action items on your presentation (that should be incorporated in the final KAON).
  • The minutes & action items from the EC meetings are posted at http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning
posted kaons
Posted KAONs
  • 415 TMT site monitoring data (restricted access)
  • 416 Atmospheric sodium density from Keck LGS photometry
  • 417 Sodium abundance data from MAUI Mesosphere
  • 419 Simple models for the prediction of Na LGS brightness & comparison to measured returns from the Gemini & Keck lasers
  • 420 Accessing the MK TMT seeing & weather data
  • 427 Variable vs fixed LGS asterism
  • 428 Implications & requirements for interferometry with NGAO
  • 429 LGS asterism geometry & size
  • 452 MOAO vs MCAO trade study report
  • 455 Science Case Requirements Document v1.0
  • 456 System Requirements Document v1.1
  • 459 NGAO System Design Phase Report #1
  • 461 Wavefront error budget predictions & measured performance for current & upgraded Keck AO
  • 462 Keck AO upgrade trade study
  • 463 Lessons learned on LGS operations: weather impact, efficiency & science ops model
  • 465 NGAO LGS wavefront sensor: Type & number of subapertures trade study
  • 466 Computer simulations of AO PSFs for NGAO
  • 468 An algorithm for reconstruction of Keck Telescope segment figure errors
  • 470 Keck NGAO sky coverage modeling
  • 472 GLAO for non-NGAO Instruments
  • 473 NGAO System Design Phase Report #2
  • 474 AO Photometry for NGAO
  • 475 Tomography codes comparison & validation for NGAO
  • 476 Observing Models trade study
reasons for replan
Reasons for Replan
  • Significantly behind schedule
  • Behind on earned value: 29% of labor & dollars spent, but plan only 24% complete
  • Planned opportunity (scheduled in SEMP) to revisit plan approach, priorities, tasks, personnel, dictionary definitions, etc.
  • We also need to improve how we are managing this project
    • Schedule and budget are tools in accomplishing the project
replan
Replan

http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/SystemDesignPhasePlanning/NGAO_SD_schedule_v24.mpp

changes made in replan
Changes made in Replan
  • Excel summary of MS Project changes between versions 20 & 24 posted at http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/SystemDesignPhasePlanning/NGAO_SD_schedule_v24.xls
  • Highlights what’s changed.
budget
Budget

Reduction in replan labor largely due to removing 1230h of students

next steps
Next Steps
  • Complete Replan with Team’s input
    • Determine how to proceed with System Architecture
    • New & revised WBS dictionary definitions
    • Improved management strategies
    • More focused team
    • Redo team meeting goals
  • Complete the following items in May:
    • SCRD & SRD v2
    • FRD v0 & Science Instruments FRD v1
    • Performance budgets summary
    • Trade Studies
    • Define Candidate Subsystems

+ Remember to do work scope planning sheets for new tasks