An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NGAO System Design:AO System (WBS 3.2) & Laser Facility (WBS 3.3) DesignInputs & Outputs Peter Wizinowich NGAO Team Meeting #9 August 24, 2007

  2. Presentation Sequence • Inputs • KAON summary table (includes all of the inputs) • Management Plan • Requirements (SCRD, SRD, FRD) • Performance Budgets • Trade Studies • System Architecture (see next presentation) • Outputs • Conceptual Designs • Functional Requirements

  3. Inputs: KAONs http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/NewKAONs/KAON_summary.xls

  4. Management Plan • System Design Phase Planning http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning • WBS dictionary defines each WBS element See appendix 9 of KAON 414 Systems Engineering Management Plan (SEMP) http://www.oir.caltech.edu/twiki_oir/bin/viewfile.cgi/Keck/NGAO/SystemDesignPhasePlanning?rev=2;filename=NGAO_SD_System_Eng_Mgmt_Plan_v20.doc • MS Project Plan defines WBS elements, resources & schedule (see KAON 481 for mid-year replan) http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/SystemDesignPhasePlanning/NGAO_SD_schedule_v26.mpp See next 2 slides • See previous presentation for design phase management details

  5. Management Plan – WBS 3.2

  6. Management Plan – WBS 3.3

  7. Inputs: Requirements • Overview of Requirements documents http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/070824_Remote_NGAO_Meeting_9/Overview_of_NGAO_Requirements_Documents.doc • Science Case Requirements Document (SCRD) http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/NewKAONs/NGAO_SCRD_Release1.pdf • 1-page science requirements summary (next slide) http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/070824_Remote_NGAO_Meeting_9/Architecture_reqments_summary_v7.xls • System Requirements Document (SRD) http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/NewKAONs/KAON456_NGAO_SRD_v1.13.doc • Instrument Baseline Requirements Document http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/WorkProducts/Baseline_Requirements_Document.doc • Functional Requirements Document (FRD) http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/WorkProducts/KAON_NGAO_FRD_v0.1.doc • Sample: section 7.2 from draft FRD http://www.oir.caltech.edu/twiki_oir/bin/viewfile.cgi/Keck/NGAO/070824_Remote_NGAO_Meeting_9?rev=1;filename=Sec72_AO_EncOpticalRelay.doc

  8. Inputs: Science Require-ments http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/070824_Remote_NGAO_Meeting_9/Architecture_reqments_summary_v7.xls

  9. Outputs The AO system & laser facility design efforts are expected to produce the following: • A revised & complete set of functional requirements for each WBS element • These will be incorporated into the FRD (they should be provided in the FRD format) • FRD configuration management is TBD • Likely 1 person to approve/release minor changes & draw major changes to EC’s attention • These can include redistribution of the performance budgets • One or more design concepts for each WBS element that demonstrate feasibility to satisfy the functional requirements • A KAON documenting the products of each WBS element • Especially, the design concept & its evaluation versus the functional requirements • Also, results of any trades or analyses, identification of any issues and/or technical risks & suggested risk mitigation • Appropriate WBS elements can be grouped together in a KAON • These KAONs will be used as a basis for the preliminary design • Cost information is not an expected output of this phase, however any relevant cost information should be provided for inclusion in WBS 4.1.2 (costing) • The overall design will be documented in the System Design Manual (SDM) with reference to the KAONs and FRD