An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 0 PHASE II ESA 2014 ESA GUIDELINES

  2. PHASE II ESA • PROJECT DEVELOPMENT PROCESSES • PATH 2 AND 3 PROJECTS • PATH 4 AND 5 PROJECTS W/ WORK PLAN 2014 ESA GUIDELINES

  3. PHASE II ESA • A PHASE II ESA IS USED TO DETERMINE THE ABSENCE OR PRESENCE OF SUSPECTED CONTAMINATION WITHIN THE ROW • DETERMINE THE WASTE CLASSIFICATION • SOLID WASTE • NON-HAZARDOUS • HAZARDOUS • MAY BE USED TO DETERMINE THE EXTENT 2014 ESA GUIDELINES

  4. PHASE II ESA PHASE II ESA IS USED TO PROVIDE A HIGHER DEGREE OF CONFIDENCE IN REGARD TO THE ENVIRONMENTAL RISK INVOLVED IN TAKING ROW OR WHOLE PROPERTIES 2014 ESA GUIDELINES

  5. PHASE II ESA • RIGHT OF ENTRY • ODOT AND ITS CONSULTANT HAVE THE RIGHT TO ENTER THE ROW OR PROPERTIES TO CONDUCT NECESSARY TESTING • PROPERTY OWNER MUST BE NOTIFIED 48 HOURS IN ADVANCE 2014 ESA GUIDELINES

  6. PHASE II ESA • THE WORK MUST BEGIN NO MORE THAN 30 DAYS FROM THE DATE OF NOTIFICATION • THE CONSULTANT SHOULD NEVER SIGN AN ACCESS AGREEMENT WITH THE OWNER 2014 ESA GUIDELINES

  7. PHASE II ESA WORK PLAN • INTRODUCTION • FIELD ACTIVITIES/SAMPLING PROCEDURES • SOIL BORING/MONITORING WELL LOCATIONS • SAMPLING METHODS • FIELD SCREENING AND SAMPLE SELECTION • ANALYTICAL METHODS • QUALITY ASSURANCE / QUALITY CONTROL • GEOPHYSICAL SURVEY (IF APPLICABLE) • SITE DIAGRAM • PROJECT MANAGEMENT PLAN 2014 ESA GUIDELINES

  8. PHASE II ESA • PHASE II ESA ASSESSMENT IS BASED ON AN OES IOC RECOMMENDATION FOR FURTHER ASSESSMENT • EITHER BASED ON AN APPROVED WORK PLAN; • OR, OES IOC WITH DIRECTION OF WHAT WORK TO COMPLETE 2014 ESA GUIDELINES

  9. HEALTH AND SAFETY PLAN • A SITE SPECIFIC HEALTH AND SAFETY PLAN IS REQUIRED UNDER 29 CFR 1910.120 • THE SAFETY PLAN SHOULD NOT BE SUBMITTED TO ODOT FOR APPROVAL OR • SHOULD NOT BE INCLUDED IN THE PHASE II REPORT 2014 ESA GUIDELINES

  10. PHASE II ESA ASSESSMENT • IN ALL CASES, THE OES IOC IS CONSIDERED THE FINAL DECISION FOR THE PHASE II ESA DOCUMENT 2014 ESA GUIDELINES

  11. PHASE II ESA • FIELD WORK • OWNER NOTIFICATION COMPLETE • OUPS AND LOCATORS NOTIFIED IN ADVANCE • ALL DIRECTION COORDINATED • AUTHORIZATION IN PLACE 2014 ESA GUIDELINES

  12. PHASE II ESA • PREFERED METHOD OF INVESTIGATION • DIRECT PUSH TECHNOLOGY • LESS WASTE GENERATION • SMALLER EQUIPMENT • FASTER • HOLLOW STEM AUGER • GENERATES LARGE AMOUNTS OF WASTE • AIR ROTORY • USED FOR DRILLING BEDROCK 2014 ESA GUIDELINES

  13. DIRECT PUSH TECHNOLOGY 2014 ESA GUIDELINES

  14. PHASE II ESA • BORINGS • DESIGNATED LOCATIONS & DEPTH • VARIATIONS MUST BE APPROVED BY OES • MONITORING WELLS • IF REQUESTED, • PROPER DEPTH & SCREEN LENGTH • WITHIN THE FIRST WATER BEARING ZONE 2014 ESA GUIDELINES

  15. PHASE II ESA • SOIL SAMPLE COLLECTION • CONTINOUS SAMPLE COLLECTION • HIGHEST FIELD SCREEN READING • SINGLE SAMPLE PER BORING • UNLESS CHANGE HAS BEEN AUTHORIZED OR 2014 ESA GUIDELINES

  16. PHASE II ESA • PID SCREEN READING AT ZERO (0) • SIGHT AND SMELL • SOIL SAMPLE IMMEDIATELY ABOVE SOIL/GROUNDWATER INTERFACE OR • BOTTOM OF BORING 2014 ESA GUIDELINES

  17. PHASE II ESA • GROUNDWATER SAMPLING • FROM DEVELOPED WELL • PURGED WITH MINIMUM 3 WELL VOLUMES • CLEAN DISPOSIBLE BAILER • STATIC WATER LEVELS SHOULD BE COLLECTED PRIOR TO PURGING OF WELL 2014 ESA GUIDELINES

  18. PHASE II ESA • FREE PRODUCT • IF FREE PRODUCT IS FOUND DURING GROUNDWATER SAMPLING THE CONSUTANT SHOULD IMMEDIATELY NOTIFY THE DISTRICT ENVIRONMENTAL COORDINATOR OF THE SITUATION • THE OWNER OF THE PROPERTY SHOULD THEN BE NOTIFIED OF THE PRESENCE OF PRODUCT ON HIS PROPERTY 2014 ESA GUIDELINES

  19. PHASE II ESA • SAMPLE PREPARATION • PROPER SIZED LAB CONTAINERS • LABELED • PROTECTED • ICED • COMPLETED CHAIN OF CUSTODY • ALL IN ICE CHEST FOR SHIPPING 2014 ESA GUIDELINES

  20. PHASE II ESA • GEOPHYSICAL SURVEY • IF REQUESTED • TO DETERMINE PRESENCE OF STRUCTURES LIKE UNDERGROUND TANKS OR OBJECTS 2014 ESA GUIDELINES

  21. PHASE II ESA • EXCEPTIONS: • NEAR SURFACE SAMPLNG • SHALLOW BORINGS (SOIL ONLY) • SEDIMENT SAMPLES (HAND PROBE) • LAND FILL SAMPLING (OAC 3745-27-13) 2014 ESA GUIDELINES

  22. ANALYTICAL • TYPICAL: • VOC - (SW 846 METHOD 8260) • SVOC- (SW 846 METHOD8270) • TPH (GRO, DRO, & ORO) (METHOD 8015B) • RCRA METALs- (SW 846 METHOD6010) 2014 ESA GUIDELINES

  23. BORING/WELL SEALING • BORINGS: • BENTONITE PELLETS AND HYDRATION • MONITORING WELLS: • STATE COORDINATING COMMITTEE ON GROUNDWATER TECHNICAL GUILDELINES FOR SEALING UNUSED WELLS 2014 ESA GUIDELINES

  24. REPORTING • Phase II ESA Report Requirements • Executive Summary • Signature Page • Introduction • Background Information • Geological Information, Physical Setting, Regional Hydrology 2014 ESA GUIDELINES

  25. REPORTING • Geophysical Survey Discussion • Field Activities and Sampling Procedures • Geophysical Survey • Field Screening and Sample Selection • Analytical Test Results • Quality Assurance/Quality Control • Findings, Data Evaluation and Regulatory Interpretation 2014 ESA GUIDELINES

  26. REPORTING • Geophysical Survey Results • Field Screening Results • Boring Log Descriptions • Analytical Test Results • Quality Assurance/Quality Control • Conclusions and Recommendations 2014 ESA GUIDELINES

  27. REPORTING • Appendices • Project location maps (including topographic and county maps) • Diagrams with sampling locations • Potentiometric (if necessary) • Geophysical survey report • Soil boring logs 2014 ESA GUIDELINES

  28. REPORTING • Laboratory analytical reports and chain of custody • Other regulatory reports and/or data (if necessary) 2014 ESA GUIDELINES

  29. PLAN NOTES • PCS – PETROLEUM CONTAMINATED SOIL PLAN NOTE • SOLID/HAZARDOUS WASTE PLAN NOTE • REGULATED WATER PLAN NOTE 2014 ESA GUIDELINES

  30. PLAN NOTES • PLAN NOTES ARE EITHER DEVELOPED BY OES, DISTRICT OR CONSULTANT • PLAN NOTE IS TO DESCRIBE THE MANAGEMENT OF THE MATERIALS DURING CONSTRUCTION 2014 ESA GUIDELINES

  31. PLAN NOTES • PLAN NOTES ARE INCORPORATED INTO THE CONSTRUCTIO PLANS AS PART OF THE CONSTRUCTION CONTRACT 2014 ESA GUIDELINES

  32. REMEDIAL DESIGN • FOR PROPERTIES WHERE CONTAMINATION IS PRESENT THEN A REMEDIAL DESIGN PLAN MAY BE DEVELOPED TO ENSURE THAT THE MATERIAL IS MANAGED CONSISTENT WITH THE APPROPRIATE ENVIRONMENTAL REGULATIONS 2014 ESA GUIDELINES

  33. INVESTIGATION DERIVED WASTE • WASTE MATERIALS SHOULD BE MANAGED AND DISPOSED OF IN ACCORDANCE WITH ODOT’s REVISED GUIDANCE REGARDING MANAGEMENT OF INVESTIGATION DERIVED WASTE (APPENDIX N) 2014 ESA GUIDELINES