ARIS – MS Project Interface

DESCRIPTION

ARIS – MS Project Interface. The Aris-MS Project interface converts functions, rules, resources and events from ARIS Toolset Version 4.03 or higher to MS Project 98 or higher and vice versa. ARIS – MS Project Interface.

1 / 17

Download Presentation

ARIS – MS Project Interface

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ARIS – MS Project Interface • The Aris-MSProject interface converts functions, rules, resources and events from ARIS Toolset Version 4.03 or higher to MSProject 98 or higher and vice versa.

  2. ARIS – MS Project Interface • This interface supports more than 150 ARIS attributes and more than 300 MS Project properties. • The interface can be applied to the following ARIS models: eEPC, eEPC (Instance), eEPC as column display, eEPC with material flow, PPC, Office process, Industrial process, PCD, PCD with material flow or Value added chain diagram.

  3. ARIS Report • This interface consists of two reports:ArisToMSProject report, for exporting ARIS models into MS Project, andArisFromMSProjectreport, for importing the MS Project data into ARIS.

  4. Data Transfer Configuration • You can viewand edit the active configuration of data transfer from ARIS to MS Project and vice versa.

  5. Edit Transfer Configuration • All attributes, which can be transferred, are listed in theleft window, and all attributes, which will be transferred, are listed in the right window.

  6. Add Field toConfiguration

  7. Add Field toConfiguration

  8. Remove Field from Configuration

  9. Remove Field from Configuration

  10. Assignments • First option allows you to choose how many sublevels you want to include in data transfer. • Second option means that, for each assignment, you will be asked whether you want to include that assignment in transfer or not.

  11. Connections

  12. Connections You also choose the way connections will be handled. Connections can be handled in any of the following ways: • all connections will be handled as if they were active (if so, you can also update the model – all connections will be marked as active) • connections will be handled the way you set them • you will be asked to resolve unclear situations regarding connections to/from rule objects (if so, you can decide whether you want AND and/or OR rule object types to be handled automatically).

  13. Data Transfer • During the data transfer, the program status window will be displayed.

  14. Data Transfer • This message will be displayedat the end of data transfer.

  15. MS Project File

  16. IDS Scheer Newsletter 2/2000 • The ARIS – MS Project Interface enables users to combine the benefits of ARIS in business process modeling and the benefits of MS Project’s handling of these models as projects. • Bernd Guertler of BBP Energy GmbH, the first customer for this interface: "...First of all, I would like to let you know that I am very impressed with your Interface and that I will promote it in our user group and on the international ARIS Forum in Dusseldorf...."

  17. Information • The interface price is 2000EURper user. • More information about the ARIS – MS Project Interface at aris-project@enel.hr http://www.enelsoftware.com/