Status of Readout Boards and Gas Monitor. Craig Woody BNL. Upgrade Working Group July 18, 2006. Schedule for Readout Boards. More than half of the boards (10/16 for each side) have been fabricated. Remaining boards should be finished by Friday.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Status of Readout Boards and Gas Monitor' - cameron-adams


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Status of readout boards and gas monitor

Status of Readout Boards

and Gas Monitor

Craig Woody

BNL

Upgrade Working Group

July 18, 2006


Schedule for readout boards
Schedule for Readout Boards

  • More than half of the boards (10/16 for each side) have been

    fabricated. Remaining boards should be finished by Friday.

  • One board of each type has been stuffed by the stuffing house and

    tested at BNL. Both work fine. Stuffing of remaining 9 of each started

    on Monday and will be ready on Thursday (7/20). Remaining boards

    will be finished about a week later.

  • Feed through connectors will be added at BNL and then tested.

    Test fixture being constructed to speed up testing (expect to take

    ~ 1 hour/board).

  • Gluing procedure for rohacell has been tested and works. Boards

    will be glued after testing. Rate will be 4/day. Expect first boards to

    be ready to send to Stony Brook ~ 7/26

  • Will construct fixture to help facilitate installing boards on back of

    detector.

C.Woody, HBD Working Group Meeting, 7/18/06


Final readout board
Final Readout Board

First RHS board (IO1260)

Mfg: RD Circuits

C.Woody, HBD Working Group Meeting, 7/18/06


Test pulse distribution
Test Pulse Distribution

M.Rumore

C.Woody, HBD Working Group Meeting, 7/18/06


Gas monitor
Gas Monitor

  • Gas Monitor arrived at BNL 7/6. Looks good !

  • Have begun setting up Labview controls of spectrometer grating

    and current switch for picoammeters.

  • Other parts (phototube housings, windows, test cells, etc.) are being

    fabricated. Some are already finished, some will be ready within a

    week or two.

  • We have decided to add a small turbo pump to the spectrometer and

    mirror box. This will allow us to measure the gas transmission relative

    to vacuum rather than argon. With a relatively small modification to

    the gas lines for the argon, can also pump on test cells for calibration

    for vacuum transmission.

  • Estimate ~ one month to complete entire system.

C.Woody, HBD Working Group Meeting, 7/18/06


Gas transmission monitor
Gas Transmission Monitor

C.Woody, HBD Working Group Meeting, 7/18/06