Transmission Policy. Overview of the Transco’s Operation within the Partnership SPP RTO. SERC Sys Op Conf March 7, 2001. ENTERGY TRANSCO Partnership with SPP. Send inquiries to: Tim Ponseti email: tponset@entergy.com phone: 870-541-3924. AMEREN. AECI. EDE. TVA. SPA. Entergy. OG&E.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Overview of the Transco’s Operation within the Partnership SPP RTO' - blue


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide2

ENTERGY TRANSCO Partnership with SPP

Send inquiries to: Tim Ponseti

email: tponset@entergy.com

phone: 870-541-3924

slide3

AMEREN

AECI

EDE

TVA

SPA

Entergy

OG&E

BATESVILLE

SMEPA

CSW

SOUCO

CLECO

CAJUN

LEPA

LAFA

Entergy Interfaces

75 Transmission Interconnections with 14 Systems

slide4

The roadmap for future operation of the transmission system has been radically altered by FERC order 2000

“To infinity, and beyond.”

Buzz Lightyear

rto market structure for the spp partnership rto is still under development
RTO Market Structure for the SPP Partnership RTO is still under development
  • Reached agreement on a hybrid structure
      • Team formed (CMSWG) to work out the details
  • LMP for real-time balancing energy market
  • Combination of financial rights and physical rights for development of forward market
      • Not clear how forward market will develop but LMP with financial rights will be the baseline market structure.

“In theory, there is no difference between theory and practice. But, in practice, there is.”

Jan L.A.van de Snepscheut

slide6

The SPP will not be collapsed into a single Control Area (yet?)

  • A control area is an electrical system bounded by interconnection (tie line) metering and telemetry. It controls its generation directly to maintain its interchange schedule with other control areas and contributes to frequency regulation of the Interconnection
  • A CA controls its actual interchange and contributes to Interconnection frequency by adjusting its generation through its automatic generation control system (AGC).
  • The Transco will be the Control Area for the Transco footprint
ancillary services under the partnership rto
Ancillary Services under the Partnership RTO
  • Service RTO Transco
  • #1 Scheduling 
  • #2 Voltage 
  • #3 Regulation 
  • #4 Imbalance 
  • #5 Op Reserves spinning 
  • #6 Op Reserves supplemental 

6

key milestones

2002

2000

2001

Oct

Nov

Dec

Key Milestones

Key Milestones

Sourcing/Staffing Begins

Assets or operational control transferred to TransCo by TransCo participants

Select Facility Sites (Primary, Backup & Headquarters)

Begin Selection of TransCo Board of Directors

LMP Parallel Operation

FERC approval of TransCo

IT Shared Corporate System Split

TransCo Blueprint Implementation Team Kick-Off

Mgt. Team Selected

File changes to TransCo rate schedules with FERC

TransCo Board of Directors Selected

LMP Operational

Q4

Q1

Q2

Q3

Q4

TOC/OIC Split

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

T&D IT Split

Texas Pilot Mock Market begins

EMO Split

SPP/TransCo Market Trials Begin

TransCo Blueprint Complete

RTO Market Rules

TransCo independent operation begins

RTO Procedures & protocols for Partnership finalized

Migrate to new facilities

TransCo commercial terms finalized (205 filing)

Migrate EMS to Pine Bluff

FERC Filing

Internal Integration Test for SPP Begins

FERC filing (rate schedule proposal) (205 filing)

Key

Texas Pilot Begins

SPP Milestones

TransCo Milestones

rto day one operations
RTO Day One Operations
  • Full congestion Management System will not be in place for Day One operations
    • No FTR/FGRs
    • Will still use TLRs to resolve congestion
  • RTO will provide a Balancing Market and Reserve Market.
    • Regulation Market not in place. CAOs to provide regulation service
  • SPP will calculate Net Scheduled Interchange every 15 minutes for each control area based on bilateral schedules and deployment of balancing energy. This NSI will be used by each control area to manage their ACE.
  • Transco will send EMO a “net signal” indicating the energy balance for Entergy Opcos net of IPP generation inside the Opco’s territories
spp membership
SPP Membership
  • Entergy has rejoined the SPP now as a Non-Transmission Owner
      • Ability to participate as members of RTO Teams
      • Ability to officially vote on issues as any other member
      • Primary membership will remain at SERC until FERC approval of SPP RTO and Transco
      • Upon FERC approval, the Transco will become a full member of the SPP RTO
  • The Transco plans to remain active in SERC and maintain some type of active associate membership.
entergy transco ops
Entergy TRANSCO Ops

TRNG

DESK

XMSN

DESK

SCHED

DESK A

SCHED

DESK B

GIS

DESK

TAG TS

DESK

RTA

DESK

Shift Mgr

DESK

slide14

ENTERGY TRANSCO Partnership with SPP