1 / 11

CF Role in Transition to Occupancy & Operations

CF Role in Transition to Occupancy & Operations. Marty Fallier Conventional Facilities Advisory Committee Review November 9-10, 2009. Outline. Beneficial Occupancy – Definition & Criteria Transition to Operations Planning CF Support to Operations Related NSLS-II Facility Issues

Download Presentation

CF Role in Transition to Occupancy & Operations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CF Role in Transition to Occupancy & Operations Marty Fallier Conventional Facilities Advisory Committee Review November 9-10, 2009

  2. Outline • Beneficial Occupancy – Definition & Criteria • Transition to Operations Planning • CF Support to Operations • Related NSLS-II Facility Issues • LOB Build-out • Remote End Stations / Long Beamlines • Building 725 • JPSI

  3. Beneficial Occupancy • For this contract, beneficial occupancy (BO) is defined as: • Completion of all contract deliverables for a designated space except for punchlist items • Includes availability of all utilities at designed capacity • Allows that HVAC may not be fully tuned to meet final specs • Contractor is fully aware of these requirements and is working accordingly • If there are schedule delays, these criteria can be softened • Must meet requirements to enable ASD system installation • Described in Erik Johnson’s talk • Must meet minimum BNL SBMS criteria for beneficial occupancy readiness evaluation

  4. Beneficial Occupancy cont’d • The BORE process identifies appropriate requirements for a given facility and its intended use • BNL SBMS BORE requirements typically are: • Basic building structure and envelope complete and meet all life safety egress criteria • Fire protection/detection systems tested, approved and functioning • Functioning electrical systems, communication and lighting for personnel egress and work requirements • Any ESH plans, related to the activities to be conducted, prepared and available • Ventilation and/or minimum temperature control to protect building contents • O&M trained on operating systems and O&M documentation available

  5. Ring Bldg Construction Phasing Phase Milestone Baseline 1-Feb-11 Pentant 1- BO 1 9-Feb-12 2 Pentant 5 - BO 23-Mar-11 3 RF Building - BO 2-Jun-11 4 Pentant 2 - BO 27-Sep-11 5 Pentant 3 - BO 18-May-11 Injection Building - BO 6 28-Nov-11 7 Pentant 4 - BO Ring Bldg Const. 30-Apr-12 8 Complete • Beneficial Occupancy Dates • Construction of LOBs to be Coordinated with Ring Bldg Construction Phasing

  6. Transition to Operations Planning • Transition to operations planning for an accelerator facility will be a substantial effort • Process is getting underway now led by Steve Hoey • Authorization basis workshop held August 09 to present preliminary plans and solicit input and guidance from other SME’s • Key for CF is to meet current schedule goals and assure technical quality of completed facilities • Implement effective QA program during construction of facilities • Document proper commissioning of systems • Maintain configuration control and accurate as-built documents • Additional CF requirements may be identified as planning matures • i.e. CF system interfaces related to ASD operations – WBS 1.5.4

  7. CF Support to Operations • Although operations are ~4+ years off, CF staff will be required to support some operational elements • Engineering and operating guidance as CF utility systems and services are placed under load and variable conditions • Addition of future LOBs or fit-out of shelled LOBs • Installation of new beamlines & User facilities • Structural and utilities/services capacity issues • Maintenance, modification and optimization of utility systems - particularly, HVAC, power and water systems • Modification of related facilities as operations and staffing levels ramp up

  8. Related NSLS-II Facilities • Additional LOBs or fit-out of shelled LOBs • Update design and manage construction as required • Minimize impacts to on-going operations • Remote End Stations and Long Beamlines • Nano-probe BL building to be added to CF scope soon • Unique vibration and environmental control requirements • Other concepts for long beamlines being considered • All have building and utility service design requirements • Joint Photon Sciences Institute • Could have substantial impact on site plan and utilities • Funding uncertainty with NY State not resolved yet

  9. Related NSLS-II Facilities cont’d • Major CF activity will be planning for future use of Building 725, the existing NSLS • Most of NSLS-II management, administrative, engineering and scientific staff will occupy B725 – a large fraction of the projected ~500 total NSLS-II staff • Current building occupancy is just ~145 • Existing NSLS accelerator (UV and VUV Rings) will have to be D&D’d • Need to plan for future conversion of this space into usable space for: • Technical support areas, shops, labs, for fabrication and testing • Possible conference or auditorium space • Integrated with existing office space to meet total staff space requirements

  10. NSLS-II Site Plan NSLS-II With Full LOB Build-Out N 100 0 200

  11. Conclusions • Planning for transition to operations is just getting underway and CF role is largely well defined • Some detail requirements may be forthcoming • WBS 1.5.4 Integrated control and communication should be able to address most of these • Planning for work outside the current CF project scope is just getting underway • Anticipate greater CF involvement and implementation of planning activities for other facilities: B725; JPSI; long beamlines, LOBs • CFAC experience and guidance in these areas would be valuable

More Related