Atlas standard opening

Atlas standard opening. Run configuration. Side C. Side C. Side A. Side A. In run, the components dedicated to the movement of the detectors are stored at surface. The first operation, as soon as shaft C is opened, is to lower these equipments and to connect them.

amanda
Download Presentation

Atlas standard opening

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Atlas standard opening

  2. Run configuration Side C Side C Side A Side A In run, the components dedicated to the movement of the detectors are stored at surface. The first operation, as soon as shaft C is opened, is to lower these equipments and to connect them. The heavy trucks are compressed and used to support JFS shielding. The light trucks are at surface, ready to be lowered and used as support structure for the Toroid end caps.

  3. Step 1 : shielding removing Side C Side C Side A Side A

  4. Step 1 : shielding removing (2) Side C Side C Side A Side A

  5. Step 1 : shielding removing (3) Side C Side C Side A Side A

  6. Step 1 : shielding removing (4) Side C Side C Side A Side A

  7. Step 2 : Barrel opening - A side Side C Side A Side C Side A

  8. Step 3 : Barrel opening - C side Side C Side A Side C Side A

  9. Step 4 : Access completion Side C Side A Side C Side A

  10. List of procedures List of tooling for shielding removing ATL-HT-OP-0010, EDMS Id 970117 JFS3 Removing using compressed truck ATL-HT-OP-0009, EDMS Id 969888 BW movement ATL-HT-OP-0012, EDMS Id 972580 JFC2 & JFC3 removing ATL-HT-OP-0009, EDMS Id 969888 JFC1 removing using compressed truck ATL-HT-OP-0009, EDMS Id 969888 Truck lowering and connection ATL-HT-OP-0011, EDMS Id 971453 TE movement ATL-HT-OP-0011, EDMS Id 971453 JD/SW movement ATL-HT-OP-0011, EDMS Id 971453 AE movement ATL-HT-OP-0011, EDMS Id 971453 PPSPS for ATLAS opening operation ATL-HT-EY-0003, EDMS Id 971452 PPSPS for Shielding removing ATC-TY-EY-0116, EDMS Id 971609 PPSPS for Big Wheels movement ATC-TY-EY-0115, EDMS Id 971615