An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Team 5Prototype Fabrication, Economic and Test Plan QDR Presented By: Maria Mullins Charles Stangle

  2. Outline • Aircraft Characteristics • Overall Schedule • Economic Plan • Flight Test Plan AAE 451 – Team 5

  3. Aircraft Characteristics • Wing Span: 3.236 ft • Estimated Weight: 0.878 lb • Neutral Point: 0.728 ft • Center of Gravity: 0.619 ft • Static Margin: 0.150 AAE 451 – Team 5

  4. Overall Schedule • To be accomplished before 1st flight • Order parts – March 10 • Build prototype wing – March 11 • Test prototype strength – March 22 • CDR – March 24 • CNC Parts – by March 28 • Fiberglass Parts – by April 3 • Build – by April 7 • Test and Rebuild – until flight date AAE 451 – Team 5

  5. Economic Plan – Materials AAE 451 – Team 5

  6. Economic Plan – Electronics Total Materials/Electronics Cost: $508.81 AAE 451 – Team 5

  7. Economic Plan – Flight Test • Flight Testing Cost • 5 hours is a conservative estimate • Allows for extra time to deal with problems • (8 Men + 1 Woman) X 5 Hours = 45 Person-Hours AAE 451 – Team 5

  8. Economic Plan – Prototype Fabrication • Foam – “Borrowed” • Fiberglass Sample - $4 • Epoxy/Vacuum Bag/Bleeder Cloth/Breather Cloth – Also “Borrowed” • 2 MEN X 5 Hours = 10 MAN-Hours • Passing Senior Design – Priceless AAE 451 – Team 5

  9. Economic Plan – Total Person-Hours • So Far – 1100 Person-Hours • CNC and Fiberglass – • 10 Hours X 2 People = 20 Person-Hours • System Integration – • 10 Hours X 9 People = 90 Person-Hours • Pilot Cost – 2 Hours AAE 451 – Team 5

  10. Economic Plan – Total Cost • 1222 Person-Hours X $50 per Hour = $61100 • Total Material and Prototype Cost – $508.81 • Total R&D and Manufacturing Cost – $61,608.80 AAE 451 – Team 5

  11. Test Plan • Test Attachments • Test Motor • Test Servos/Electrical Connections • Drop Test/Test Landing Gear • Flight Test –in Mollenkompf if available AAE 451 – Team 5

  12. Flight Test • Take-off and Climb • Unpowered Glide • Turning Flight/Gyro Control • Propeller Optimization Testing • Purchased 3 possibilities AAE 451 – Team 5

  13. Questions? AAE 451 – Team 5